Inspection History Details
Inspection Status: Approved
Inspection History: GRADING - FINAL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/22/2013 | GRADING - FINAL | Approved | ||
| 06/25/2013 | GRADING - FINAL | Partial Approval | PROVIDE A CERTIFICATION STATEMENT FROM THE ENG OF RECORD STATIMG THAT ALL SITE WORK WAS SUBSTANTIALLY COMPLETED PER THE APPROVED PLAN | |
| 03/15/2013 | GRADING - FINAL | Continued | NO SIGNIFICANT CHANGES AND/OR CONCERNS AT THIS TIME | |
| 03/07/2013 | GRADING - FINAL | Partial Approval | 1) CONTRACTOR AWAITING TO COMPLETE WORK ALONG THE LANDSCAPE BUFFER AT THE WEST SIDE OF THE SITE. 2) NEED TO COMPLETE CONSTRUCTION OF THE WEST ENTRANCE OFF OF HOUGHTON. 3) PROVIDE BASIN/STORM DRAINAGE CERT 4) CPMPLETE HC PARKING AND ACCESS 5) COMPLETE STRIPING 6) COMPLETE INSTALL OF FENCING 7) AN AS-BUILT WAS SUBMITTED |