Inspection History Details
Inspection Status: Approved
Inspection History: LANDSCAPE INSPECTION
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/24/2012 | LANDSCAPE INSPECTION | Approved | ||
| 02/02/2012 | LANDSCAPE INSPECTION | Partial Approval | 1) COMPLETE INSTALLATION OF DG 2) COMPLETE INSTALLATION OF ALL ROCK RIP RAP 3) REMOVE ALL RE-BAR, STAKES, AND FORMS. 4) NEED REVISED LANDSCAPE PLAN FOR FINAL INSPECTION 5) COMPLETE RET/DET BASIN AND SPILLWAY 6) COMPLETE IRRIGATION LINES AND PLANTING ON NORTH SIDE OF BLDG. |
|
| 05/31/2011 | LANDSCAPE INSPECTION | Partial Approval | SPOKE WITH THE SITE SUPERVISOR AND DISCUSSED WHAT WILL BE OUTSTANDING IN REGARDS TO THE FUTURE LANDSCAPE INSPECTION. REMINDED HIM THAT THERE ARE ISSUES WITH THE REMOVAL OF VEEGETATION THAT WAS SUPPOSE TO BE PRESERVED IN PLACE. I WAS ADVISED THAT SOME OF THE TREES THAT WERE TO BE REMOVED WERE RELOCATED TO THE AREA WHERE THE TREES HAD BEEN REMOVED ILLEGALLY AT THE REQUEST OF THE PROPERTY OWNER OUTSIDE THE SOUTHWEST CORNER OF THE SITE. ADVISED THAT THEY SCHEDULE AN INSPECTION WITH MIKE RUSSO SO THAT HE CAN NOTE WHAT HAS BEEN DONE AT THIS TIME AND THE SPECIMEN OF TREES THAT HAVE BEEN RELOCATED. THEY ALSO NEEDED TO WORK WITH JOSEPH LINVILLE TO MAKE SURE THAT THE WORK DONE OR P0ROPOSED IS ACCEPTABLE FOR OUR MITIGATION PROCESS. |