Inspection History Details
Inspection Status: Approved
Inspection History: STORMWATER FOLLOW-UP INSP
Permit Number - T10BU01020
Inspection Description - STORMWATER FOLLOW-UP INSP
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
06/07/2011 | STORMWATER FOLLOW-UP INSP | Approved | ALL CONSTRUCTION INSPECTIONS FOR ENGINEERING, AND LANDSCAPE WILL BE ADDRESSED UNDER GRADING PERMIT #T10BU01122. | |
03/22/2011 | STORMWATER FOLLOW-UP INSP | Correction Required | CORRECT ITEMS #2 AND #4 FROM PREVIOUS STORM WATER COMPLIANCE INSPECTION DONE 2/28/11. COMPLY BY 2 WEEKS, NON-COMPLIANCE WILL RESULT IN A NOTICE OF VIOLATION. |
|
03/22/2011 | STORMWATER FOLLOW-UP INSP | Continued | SPOKE WITH SUPINTENDENT ABOUT CORRECTION OF STORM WATER ITEMS IDENTIFIED IN LAST INSPECTION, HE STATED THAT THEY WOULD BE CORRECTED. FOLLOW UP INSPECTION WILL BE DONE. | |
03/01/2011 | STORMWATER FOLLOW-UP INSP | Correction Required | 1) RE-ESTABLISH SEDIMENT CONTROLS ALONG THE PERIMETER - SOME NEEDS REPLACING. 2) REMOVE ALL EQUIPMENT AND/OR MATERIALS FROM ON TOP OF SILT SOCK - SEDIMENT CONTROLS. 3) RE-ESTABLISH YOUR STABILIZED CONSTRUCTION ENTRANCE - IT HAS SILTED IN. 4) PROVIDE ALL DOCUMENTATION FROM STORM WATER SELF INSPECTIONS PERFORMED EVERY 2 WEEKS AND AFETR A RAIN. WILL FOLLOW UP IN 2 WEEKS - PLEASE CORRECT ITEMS LISTED ABOVE. NO SITE WORK AT THIS TIME |
|
01/28/2011 | STORMWATER FOLLOW-UP INSP | Continued | MET WITH SUPERINTENDENT, DISCUSSED STORM WATER REQUIREMENTS AND PROJECT STATUS. CONTRACTORS ARE NOW BACKFILLING AND BLDG THE FOUNDATION FOR THE BLDG. REMEDIATION WORK HAS BEEN COMPLETED. 1) SEDIMENT CONTROLS ARE IN PLACE. 2) STORM WATER SELF INSPECTIONS ARE BEING PERFORMED AND DOCUMENTED. 3) A STABILIZED CONSTRUCTION ENTRANCE IS BEING USED. 4) CONTRACTOR MAY NEED TO SEWEEP THE ADJACENT ACCESS ROAD MORE OFTEN. |
|
01/07/2011 | STORMWATER FOLLOW-UP INSP | Continued | NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME. NO SITE WORK BEING DONE, CONTRACTOR STILL EXCAVATING AND STABILIZING SLOPES OF HOLE. |
|
12/17/2010 | STORMWATER FOLLOW-UP INSP | Continued | NO CHANGES, NO ACTIVITY TODAY | |
11/09/2010 | STORMWATER FOLLOW-UP INSP | Correction Required | 1) TEMP RAMPS IN THE CURB-LINE ARE IN NON-COMPLIANCE W/ THE COT STORM WATER ORDINANCE. THE CONTRACTOR MUST ALLOW STORM WATER TO FLOW UNOBSTRUCTED ALONG THE CURB LINE. 2) TEMP RAMPS CAN BE INSTALLED AS LONG AS A CONDUIT IS USED TO CONVEY STORM WATER. 3) CONTINUE TO SWEEP UP TRACKED SOIL OFF OF PUBLIC ROADWAYS. 4) REMEDIATION WORK STILL BEING ACCOMPLISHED. TRUCKS ARE HAULING WASTE CONTAMINATED SOIL OFF SITE |
|
10/21/2010 | STORMWATER FOLLOW-UP INSP | Continued |