Inspection History Details
Inspection Status: Approved
Inspection History: STORMWATER FOLLOW-UP INSP
Permit Number - T10BU00919
Inspection Description - STORMWATER FOLLOW-UP INSP
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
02/22/2012 | STORMWATER FOLLOW-UP INSP | Approved | ||
08/10/2011 | STORMWATER FOLLOW-UP INSP | Correction Required | SWEEP UP SOIL OFF PUBLIC ROADWAY. SEDIMENT CONTROLS MUST REMAIN IN PLACE UNTIL THE SITE IS 100% STABILIZED. | |
08/04/2011 | STORMWATER FOLLOW-UP INSP | Continued | SWEEP UP TRACKED SOIL OFF OF PUBLIC ROADWAY | |
06/21/2011 | STORMWATER FOLLOW-UP INSP | Continued | SITE CONSTRUCTION WILL BE DONE IN PHASES. SOME CONCRETE CURB AND SIDE WALK INSTALLED. CHANGE TO ROOF DRAINAGE AT SOUTH SIDE OF BLDG. CONTRACTOR WILL TIE ROOF DRAINS INTO EXISTING CATCH BASIN SUBGRADE. NEED TO SHOW REVISION ON APPROVED PLANS. NEED TO INSPECT INSTALLATION. ACCESS ROAD CONSTRUCTION DUE TO BEGIN, ENSURE SWPPP CONTROLS ARE IN PLACE PRIOR TO PUBLIC ACCESS, ALL ACCESS MUST BE SEPARATED FROM REMAINING CONSTRUCTION. |
|
04/27/2011 | STORMWATER FOLLOW-UP INSP | Continued | NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME | |
02/11/2011 | STORMWATER FOLLOW-UP INSP | Continued | NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME. NO SITE WORK BEING DONE CURRENTLY | |
01/25/2011 | STORMWATER FOLLOW-UP INSP | Continued | MET WITH SUPERINTENDENT (RODNEY, CONCORD CONSTR. 419-4966) DISCUSSED SWPPP NON-COMPLIANCE ISSUES. 1) CONTRACTOR WILL RE-INSTALL A DESIGNATED CONCRETE/MATERIALS WASH-OUT ON SITE AND ENSURE SUBCONTRACTORS WILL USE IT. 2) CONTRACTOR WILL INSTALL A SECOND STABILIZED CONSTRUCTION ENTRANCE TO REDUCE TRACKING. 3) CONTRACTOR MUST SWEEP UP ALL TRACKED SOIL FROM THE SITE OFF THE PAVED ENTRACE TO THE SCHOOL . 4) CONTRACTOR MUST PERFORM STORM WATER SELF INSPECTIONS AND PER SWPPP AND DOCUMENT THEM |
|
01/12/2011 | STORMWATER FOLLOW-UP INSP | Correction Required | CONTRACTOR WORKING ON BLDG ONLY, NO SITE WORK AT THIS TIME. 1) INSTALL A CONCRETE/MATERIALS WASH OUT ON SITE. CONTRACTOR DISCHARGING WASTE CONCRETE AND MORTAR. 2) CLEAN UP WASTE CONCRETE. 3) ENSURE THE AREA OUTSIDE THE CONSTRUCTION SITE IS SWEPT ROUTINELY. 4) ENSURE INSTALLED SEDIMENT CONTROLS ARE MAINTAINED. CORRECT BY 2 WEEKS, NON-COMPLIANCE WILL RESULT IN A NOTICE OF VIOLATION. YES SWPPP/REVIEWER PAUL MACHADO |