Permit: T10BU00919

Parcel: 10601247B


Addresses:

266 E PASTIME RD


Inspection Status: Approved

Inspection History: STORMWATER FOLLOW-UP INSP

Permit Number - T10BU00919

Inspection Description - STORMWATER FOLLOW-UP INSP

Inspection Status - Approved

Date Description Inspector Results Comments
02/22/2012 STORMWATER FOLLOW-UP INSP Approved
08/10/2011 STORMWATER FOLLOW-UP INSP Correction Required SWEEP UP SOIL OFF PUBLIC ROADWAY. SEDIMENT CONTROLS MUST REMAIN IN PLACE UNTIL THE SITE IS 100% STABILIZED.
08/04/2011 STORMWATER FOLLOW-UP INSP Continued SWEEP UP TRACKED SOIL OFF OF PUBLIC ROADWAY
06/21/2011 STORMWATER FOLLOW-UP INSP Continued SITE CONSTRUCTION WILL BE DONE IN PHASES.
SOME CONCRETE CURB AND SIDE WALK INSTALLED.
CHANGE TO ROOF DRAINAGE AT SOUTH SIDE OF BLDG. CONTRACTOR WILL TIE ROOF DRAINS INTO EXISTING CATCH BASIN SUBGRADE. NEED TO SHOW REVISION ON APPROVED PLANS. NEED TO INSPECT INSTALLATION.

ACCESS ROAD CONSTRUCTION DUE TO BEGIN, ENSURE SWPPP CONTROLS ARE IN PLACE
PRIOR TO PUBLIC ACCESS, ALL ACCESS MUST BE SEPARATED FROM REMAINING CONSTRUCTION.
04/27/2011 STORMWATER FOLLOW-UP INSP Continued NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME
02/11/2011 STORMWATER FOLLOW-UP INSP Continued NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME. NO SITE WORK BEING DONE CURRENTLY
01/25/2011 STORMWATER FOLLOW-UP INSP Continued MET WITH SUPERINTENDENT (RODNEY, CONCORD CONSTR. 419-4966) DISCUSSED SWPPP NON-COMPLIANCE ISSUES.

1) CONTRACTOR WILL RE-INSTALL A DESIGNATED CONCRETE/MATERIALS WASH-OUT ON SITE AND ENSURE SUBCONTRACTORS WILL USE IT.
2) CONTRACTOR WILL INSTALL A SECOND STABILIZED CONSTRUCTION ENTRANCE TO REDUCE TRACKING.
3) CONTRACTOR MUST SWEEP UP ALL TRACKED SOIL FROM THE SITE OFF THE PAVED ENTRACE TO THE SCHOOL .
4) CONTRACTOR MUST PERFORM STORM WATER SELF INSPECTIONS AND PER SWPPP AND DOCUMENT THEM
01/12/2011 STORMWATER FOLLOW-UP INSP Correction Required CONTRACTOR WORKING ON BLDG ONLY, NO SITE WORK AT THIS TIME.
1) INSTALL A CONCRETE/MATERIALS WASH OUT ON SITE. CONTRACTOR DISCHARGING WASTE CONCRETE AND MORTAR.
2) CLEAN UP WASTE CONCRETE.
3) ENSURE THE AREA OUTSIDE THE CONSTRUCTION SITE IS SWEPT ROUTINELY.
4) ENSURE INSTALLED SEDIMENT CONTROLS ARE MAINTAINED.

CORRECT BY 2 WEEKS, NON-COMPLIANCE WILL RESULT IN A NOTICE OF VIOLATION.

YES SWPPP/REVIEWER PAUL MACHADO