Inspection Status: Approved
Inspection History: GRADING - TIER REV
Permit Number - T10BU00665
Inspection Description - GRADING - TIER REV
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
04/28/2011 | GRADING - TIER REV | Approved | ||
03/11/2011 | GRADING - TIER REV | Continued | INSTRUCTED TO CHECK AS-BUILT PLAN AGAINST WHAT WAS BUILT, HOWEVER SITE AND CONSTRUCTION IS NO COMPLETED. | |
10/27/2010 | GRADING - TIER REV | Correction Required | SIGNIFICANT CHANGES TO STORM WATER DRAINAGE SHOWN ON THE APPROVED GRADING PLAN. PROVIDE AN APPROVED REVISION SHOWING CHANGES MADE. 1) CONTRACTOR INSTALLED 10" PVC IN PLACE OF 12" PVC PIPE AS SHOWN ON APPROVED GRADING PLAN. 2) CONTRACTOR REPLACED 12" PVC PIPE TEE'S AND RISERS W/ 8" PVC DUE TO REQUIRED ELEVATION OF AREA DRAINS SHOWN ON PLANS. 3) CONTRACTOR PROVIDED A LEVEL IN ORDER TO SHOOT ELEVATIONS OF PIPE AND SHOW THE REQUIRED .7 FEET OF FALL IN 400' OF STORM PIPE. ELEV. SHOT'S TAKEN SHOW POSITIVE DRAINAGE IN PIPE (.6'). 4) CONTRACTOR CHANGED LOCATION OF SOME OF THE STORM DRAIN PIPE. 5) PRIOR TO FIELD APPROVAL THE CONTRACTOR MUST PROVIDE AN APPROVED PLAN SHOWING CHANGES MADE W/ THE ENG OF RECORD STAMP AND THE COT APPROVAL. 6) OK TO BURY PIPE AS SOON AS CHANGES ARE APPROVED. |