Inspection History: GRADING - INTERMEDIATE
Permit Number - T10BU00665
Inspection Description - GRADING - INTERMEDIATE
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
04/28/2011 | GRADING - INTERMEDIATE | Approved | ||
03/11/2011 | GRADING - INTERMEDIATE | Continued | SITE NOT COMPLETED, ONE BLDG STILL UNDER CONSTRUCTION. SITE WORK NOT COMPLETED. RIGHT OF WAY WORK STILL TO BE DONE. | |
03/03/2011 | GRADING - INTERMEDIATE | Continued | SITE BEING PAVED, CURB BEING POURED. NO SIGNIFICANT CONCERNS AT THIS TIME. SWEEP UP TRACKED SOIL OFF PUBLIC ROADWAYS. NO OTHER STORM WATER CONCERNS AT THIS TIME |
|
02/07/2011 | GRADING - INTERMEDIATE | Continued | MET WITH SUPERINTENDENT, LOOKED AT NEW SIDEWALK SLOPES ALONG NE CORNER OF PHASE II. SLOPES OK . CONTINUE TO COMPLY WITH SWPPP UNTIL SITE IS COMPLETED. | |
01/07/2011 | GRADING - INTERMEDIATE | Continued | ENSURE SLOPES ON ACCES WAYS AND SIDEWALKS ARE <5%. SOME SIDEWALKS BEING POURED, CONTRACTOR MOSTLY WORKING ON BLDGS. 1) SWEEP UP TRACKING OFF OF FAIRVIEW MORE OFTEN. 2) ENSURE STOR WATER SELF INSPECTIONS ARE PERFORMED AND DOCUMENTED UNTIL THE SITE IS STABILIZED. 3) USE CONCRETE WASH OUT WHEN POURING CURBS AND WALKWAYS |
|
10/27/2010 | GRADING - INTERMEDIATE | Correction Required | SIGNIFICANT CHANGES TO STORM WATER DRAINAGE SHOWN ON THE APPROVED GRADING PLAN. 1) CONTRACTOR INSTALLED 10" PVC IN PLACE OF 12" PVC PIPE AS SHOWN ON APPROVED GRADING PLAN. 2) CONTRACTOR REPLACED 12" PVC PIPE TEE'S AND RISERS W/ 8" PVC DUE TO REQUIRED ELEVATION OF AREA DRAINS SHOWN ON PLANS. 3) CONTRACTOR PROVIDED A LEVEL IN ORDER TO SHOOT ELEVATIONS OF PIPE AND SHOW THE REQUIRED .7 FEET OF FALL IN 400' OF STORM PIPE. ELEV. SHOT'S TAKEN SHOW POSITIVE DRAINAGE IN PIPE (.6'). 4) CONTRACTOR CHANGED LOCATION OF SOME OF THE STORM DRAIN PIPE. 5) PRIOR TO FIELD APPROVAL THE CONTRACTOR MUST PROVIDE AN APPROVED PLAN SHOWING CHANGES MADE W/ THE ENG OF RECORD STAMP AND THE COT APPROVAL. 6) OK TO BURY PIPE AS SOON AS CHANGES ARE APPROVED. |