Inspection Status: Approved
Inspection History: FIRE SPKLR - UG, PIPING, HYDRO
| Date |
Description |
Inspector |
Results |
Comments |
| 06/14/2010 |
FIRE SPKLR - UG, PIPING, HYDRO |
|
Approved |
200 PSI TEST FOR 2 HOURS APPROVED |
| 05/12/2010 |
FIRE SPKLR - UG, PIPING, HYDRO |
|
Partial Approval |
OK TO BURY PIPING TO FIRE HYDRANTS X2 |
| 05/06/2010 |
FIRE SPKLR - UG, PIPING, HYDRO |
|
Not ready for Inspection |
OK TO BURY FROM 60' PIPE TO 90 DEG NORTH BEFOR TIE END. |
| 05/04/2010 |
FIRE SPKLR - UG, PIPING, HYDRO |
|
Not ready for Inspection |
OK TO BURY FROM MIDDLE OF HYDRANTS TO 60' NORTH |
| 05/03/2010 |
FIRE SPKLR - UG, PIPING, HYDRO |
|
Not ready for Inspection |
OK TO BURY FROM 100' TO MIDDLE OF TWO HYDRANTS |
| 04/30/2010 |
FIRE SPKLR - UG, PIPING, HYDRO |
|
Not ready for Inspection |
OK TO BURY FROM 45 DEG ON SOUTHEAST END TO 100' NORTH |
| 04/29/2010 |
FIRE SPKLR - UG, PIPING, HYDRO |
|
Not ready for Inspection |
Not Ready |