Inspection History Details
Inspection Status: Approved
Inspection History: BUILDING - FINAL
Permit Number - T10BU00567
Inspection Description - BUILDING - FINAL
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
07/30/2010 | BUILDING - FINAL | Approved | SHORING COMPLETE. RFI'S FOR NON-COMPLIANCES FROM E.O.R ACCEPTED. EXCAVATION TO BE MONITORED BY SURVEYOR ONCE EVERY OTHER WEEK. | |
07/27/2010 | BUILDING - FINAL | Partial Approval | ALL SHORE WALLS AT FINAL ELEVATION. SHOTCRETE STILL TO BE APPLIED AT FINAL DROPS | |
07/22/2010 | BUILDING - FINAL | Partial Approval | AT FINAL ELEVATION FOR SHORING ALONG NORTH WALL. SHOTCRETE BEING PLACED TODAY. ENGINEER'S REPORT DATED 7/16/2010 ADDRESSING NON-COMLIANCE ISSUES HAS BEEN ACCEPTED. CORRECTIONS NOTED TO BE ALLOWED. |
|
07/09/2010 | BUILDING - FINAL | Partial Approval | CUT TO FINAL ELEVATION OK ALONG EAST WALL. OTHER PROGRESS OK FOR DROPS OF SHOTCRETE AT VARIOUS LOCATIONS | |
07/07/2010 | BUILDING - FINAL | Partial Approval | 3RD DROP WHERE NORTH RAMP REMOVED OK. OTHER PROGRESS OK. | |
06/30/2010 | BUILDING - FINAL | Partial Approval | 4TH DROP @ NE CORNER OK. PINS AT SE QUAD OK FOR 4TH DROP. REVIEWED ALL SPECIAL INSPECTION REPORTS, RFI'S AND NON-CONFORMANCE ITEMS; ALL OK AT THIS TIME | |
06/28/2010 | BUILDING - FINAL | Partial Approval | 3RD DROP COMPLETE SE CORNER. 7 PINS ADDED AT TOP OF SOUTH WALL ON WEST SIDE TO ADDRESS 1/4" MOVEMENT SEEN IN LAST WEEKS SURVEY. 2 PULL TESTS DONE WITHOUT SPECIAL INSPECTOR ON SITE. I'VE ACCEPTED THE RESULTS BUT NOTIFIED CONTRACTOR THAT IF THIS HAPPENS AGAIN THEY WILL NEED TO RETEST THE PINS. |
|
06/25/2010 | BUILDING - FINAL | Partial Approval | EOR ON SITE TO REVIEW 3 AREAS (2 ON WEST, 1 ON SOUTH WALL) WHERE UPPER LIFT OF SHORING HAS MOVED DUE TO UNSTABLE SOILS. ENGINEER TO PROVIDE FIX. PROGRESS ALONG EAST WALLS OK (3RD DROP). |
|
06/24/2010 | BUILDING - FINAL | Partial Approval | 3RD DROP NEXT TO RAMPS. NAILS FOR 3RD DROP ON NORTH SIDE GOING IN OK | |
06/23/2010 | BUILDING - FINAL | Partial Approval | 2ND DROP COMPLETE FOR PERIMETER EXCEPT AT RAMPS | |
06/22/2010 | BUILDING - FINAL | Partial Approval | 2ND DROP NE CORNER OK. NAILS ALONG SW GOING IN. ENGINEER RESPONSE TO CORRECTION REPORTS REVIEWED AND ACCEPTED |
|
06/17/2010 | BUILDING - FINAL | Partial Approval | PROGRESS ON 2ND DROP WEST WALL OK. EOR NEEDS TO ADDRESS NON-COMPLIANCE NOTICES CONCERNING SOIL NAILS. OK TO KEEP WORKING AS DISCREPANCIES ARE WITHIN THE PLAN SET WHILE WORK IS WITHIN KNOWN STANDARDS FOR THIS TYPE OF SOIL RETENTION. | |
06/14/2010 | BUILDING - FINAL | Partial Approval | 1ST DROP SHOTCRETE RETAIN WALL OK FOR ENTIRE PERMITER. SOIL NAIL PROGRESS SW CORNER OK. CABLE BARRIER AT TOP OF EXCAVATION OK. | |
06/11/2010 | BUILDING - FINAL | Partial Approval | 1ST DROP SHOTCRETE RETAINING WALL AT SW OK | |
06/10/2010 | BUILDING - FINAL | Partial Approval | 1ST DROP FOR SHOTCRETE COMPLETED AT SE CORNER. | |
06/07/2010 | BUILDING - FINAL | Partial Approval | EXCAVATION TO 6' AT WEST PILING LINE OK. | |
06/04/2010 | BUILDING - FINAL | Partial Approval | PILING PROGRESS OK. LAST 65' AT NORTH END OF EAST LINE IS REFUSING THE PILES AND MAY NEED TO BE SLOPED. WAITING FOR RFI FROM ENGINEER. | |
06/02/2010 | BUILDING - FINAL | Partial Approval | PROGRESS ON SHORING PILINGS OK. HITTING PAN AT ABOUT 7', WAITING FOR RFI CONCERNING BOTTOM 2' OF PILE. |