Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit: T10BU00567

Parcel: 11717023C


Addresses:

88 E BROADWAY BL


Inspection Status: Approved

Inspection History: BUILDING - FINAL

Permit Number - T10BU00567

Inspection Description - BUILDING - FINAL

Inspection Status - Approved

Date Description Inspector Results Comments
07/30/2010 BUILDING - FINAL Approved SHORING COMPLETE. RFI'S FOR NON-COMPLIANCES FROM E.O.R ACCEPTED. EXCAVATION TO BE MONITORED BY SURVEYOR ONCE EVERY OTHER WEEK.
07/27/2010 BUILDING - FINAL Partial Approval ALL SHORE WALLS AT FINAL ELEVATION. SHOTCRETE STILL TO BE APPLIED AT FINAL DROPS
07/22/2010 BUILDING - FINAL Partial Approval AT FINAL ELEVATION FOR SHORING ALONG NORTH WALL. SHOTCRETE BEING PLACED TODAY.

ENGINEER'S REPORT DATED 7/16/2010 ADDRESSING NON-COMLIANCE ISSUES HAS BEEN ACCEPTED. CORRECTIONS NOTED TO BE ALLOWED.
07/09/2010 BUILDING - FINAL Partial Approval CUT TO FINAL ELEVATION OK ALONG EAST WALL. OTHER PROGRESS OK FOR DROPS OF SHOTCRETE AT VARIOUS LOCATIONS
07/07/2010 BUILDING - FINAL Partial Approval 3RD DROP WHERE NORTH RAMP REMOVED OK. OTHER PROGRESS OK.
06/30/2010 BUILDING - FINAL Partial Approval 4TH DROP @ NE CORNER OK. PINS AT SE QUAD OK FOR 4TH DROP. REVIEWED ALL SPECIAL INSPECTION REPORTS, RFI'S AND NON-CONFORMANCE ITEMS; ALL OK AT THIS TIME
06/28/2010 BUILDING - FINAL Partial Approval 3RD DROP COMPLETE SE CORNER. 7 PINS ADDED AT TOP OF SOUTH WALL ON WEST SIDE TO ADDRESS 1/4" MOVEMENT SEEN IN LAST WEEKS SURVEY.

2 PULL TESTS DONE WITHOUT SPECIAL INSPECTOR ON SITE. I'VE ACCEPTED THE RESULTS BUT NOTIFIED CONTRACTOR THAT IF THIS HAPPENS AGAIN THEY WILL NEED TO RETEST THE PINS.
06/25/2010 BUILDING - FINAL Partial Approval EOR ON SITE TO REVIEW 3 AREAS (2 ON WEST, 1 ON SOUTH WALL) WHERE UPPER LIFT OF SHORING HAS MOVED DUE TO UNSTABLE SOILS. ENGINEER TO PROVIDE FIX.

PROGRESS ALONG EAST WALLS OK (3RD DROP).
06/24/2010 BUILDING - FINAL Partial Approval 3RD DROP NEXT TO RAMPS. NAILS FOR 3RD DROP ON NORTH SIDE GOING IN OK
06/23/2010 BUILDING - FINAL Partial Approval 2ND DROP COMPLETE FOR PERIMETER EXCEPT AT RAMPS
06/22/2010 BUILDING - FINAL Partial Approval 2ND DROP NE CORNER OK. NAILS ALONG SW GOING IN.

ENGINEER RESPONSE TO CORRECTION REPORTS REVIEWED AND ACCEPTED
06/17/2010 BUILDING - FINAL Partial Approval PROGRESS ON 2ND DROP WEST WALL OK. EOR NEEDS TO ADDRESS NON-COMPLIANCE NOTICES CONCERNING SOIL NAILS. OK TO KEEP WORKING AS DISCREPANCIES ARE WITHIN THE PLAN SET WHILE WORK IS WITHIN KNOWN STANDARDS FOR THIS TYPE OF SOIL RETENTION.
06/14/2010 BUILDING - FINAL Partial Approval 1ST DROP SHOTCRETE RETAIN WALL OK FOR ENTIRE PERMITER. SOIL NAIL PROGRESS SW CORNER OK. CABLE BARRIER AT TOP OF EXCAVATION OK.
06/11/2010 BUILDING - FINAL Partial Approval 1ST DROP SHOTCRETE RETAINING WALL AT SW OK
06/10/2010 BUILDING - FINAL Partial Approval 1ST DROP FOR SHOTCRETE COMPLETED AT SE CORNER.
06/07/2010 BUILDING - FINAL Partial Approval EXCAVATION TO 6' AT WEST PILING LINE OK.
06/04/2010 BUILDING - FINAL Partial Approval PILING PROGRESS OK. LAST 65' AT NORTH END OF EAST LINE IS REFUSING THE PILES AND MAY NEED TO BE SLOPED. WAITING FOR RFI FROM ENGINEER.
06/02/2010 BUILDING - FINAL Partial Approval PROGRESS ON SHORING PILINGS OK. HITTING PAN AT ABOUT 7', WAITING FOR RFI CONCERNING BOTTOM 2' OF PILE.