Inspection Status: Approved
Inspection History: GRADING - INTERMEDIATE
| Date |
Description |
Inspector |
Results |
Comments |
| 04/20/2011 |
GRADING - INTERMEDIATE |
|
Approved |
Approved |
| 04/13/2011 |
GRADING - INTERMEDIATE |
|
Continued |
Spoke to Steve with ESI about the appilcation rate for the Gollia Snot on remaining distrubed areas. We agreed to a rate of 137 gal/ AC for dust control. The erosion controls measures will remain in placed and be kept in good cond. The remaining AC to be treated is 15 arces. This will be placed on 4/20. |
| 03/09/2011 |
GRADING - INTERMEDIATE |
|
Continued |
|
| 03/08/2011 |
GRADING - INTERMEDIATE |
|
Continued |
WORKING ON SIDE WALKS ON NORTH SIDE OF BUILDING AND PARKING LOT. |
| 02/16/2011 |
GRADING - INTERMEDIATE |
|
Correction Required |
Met with ESI and explained that the dirt from Costco was being placed outside of SWPPP controls and grading limits for the permit. They need to get a revised SWPP and grading plan to reflect the stockpile. |
| 09/17/2010 |
GRADING - INTERMEDIATE |
|
Continued |
SPOKE WITH STEVE REGARDING PERMIT STATUS FOR COSTCO. HE PROVIDED CONTACT INFO. COSTCO REP. WILL CALL WHEN PERMITS ARE ISSUED. |
| 09/10/2010 |
GRADING - INTERMEDIATE |
|
Continued |
REVIEWED SITE WITH JAY. STORMWATER CONTROLS ARE SUFFICIENT. WORK AT ENTRANCE NEAREST KINO. CHECKED INSTALLATION OF PIPE. |