Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Inspection History Details
Inspection Status: Approved
Inspection History: STORMWATER FOLLOW-UP INSP
Permit Number - T10BU00084
Inspection Description - STORMWATER FOLLOW-UP INSP
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
04/20/2011 | STORMWATER FOLLOW-UP INSP | Approved | Approved | |
04/13/2011 | STORMWATER FOLLOW-UP INSP | Continued | Spoke to Steve with ESI about the appilcation rate for the Gollia Snot on remaining distrubed areas. We agreed to a rate of 137 gal/ AC for dust control. The erosion controls measures will remain in placed and be kept in good cond. The remaining AC to be treated is 15 arces. This will be placed on 4/20. | |
02/16/2011 | STORMWATER FOLLOW-UP INSP | Correction Required | SWPPP controls not in place around the new stockpile of dirt from the Costco site, need to install controls | |
09/28/2010 | STORMWATER FOLLOW-UP INSP | Continued | SPOKE WITH JAY. WILL MEET ON SITE EARLY 10/10. | |
08/30/2010 | STORMWATER FOLLOW-UP INSP | Continued | RECEIVED PHONE CALL FROM COSTCO REP (425-313-6691) REGARDING STAUS OF COSTCO GRADING PERMIT. PLANS HAVE BEEN SUBMITTED HOWEVER THEY ARE WAITING TO PULL BOTH BUILDING AND GRADING PERMITS, UNTIL THE OVERALL GRADING IS NEARER COMPLETION. POSSIBLY OCT. HE WILL CALL WHEN PERMITS HAVE BEEN PULLED TO RELAY PERMIT #'S | |
08/19/2010 | STORMWATER FOLLOW-UP INSP | Continued | SPOKE WITH JAY REGARDING TRACK-OUT ON KINO. THEY ARE CALLING SWEEPER OUT. | |
08/04/2010 | STORMWATER FOLLOW-UP INSP | Continued | RIGHT-OF-WAY WORK BEING DONE OFF OF KINO. STABILIZED CONTROLS HAVE BEEN TEMP. REMOVED. SOME TRACK-OUT ON KINO DUE TO SITUATION. | |
06/23/2010 | STORMWATER FOLLOW-UP INSP | Continued | WORK CONTINUES. NO CONCERNS AT THIS TIME. | |
06/10/2010 | STORMWATER FOLLOW-UP INSP | Continued | DROVE SITE WITH JAY AND SITE SUPER TO DISCUSS STORMWATER CONTROLS. PRIMARY CONCERN IS THE S/W CORNER OF SITE NEAR EXISTING BASIN AND THE AMOUNT OF RUN-OFF THIS AREA WILL RECEIVE DURING MONSOON. | |
06/02/2010 | STORMWATER FOLLOW-UP INSP | Continued | Met with Dan with Borderland on-site, V trench for storm controls are being installed told Dan that some temp settling ponds will be needed in a few areas. We will review placement when grading activities begin. |