Permit: T10BU00084

Parcel: 13213034C


Addresses:

3434 S KINO PW


Inspection Status: Approved

Inspection History: STORMWATER FOLLOW-UP INSP

Permit Number - T10BU00084

Inspection Description - STORMWATER FOLLOW-UP INSP

Inspection Status - Approved

Date Description Inspector Results Comments
04/20/2011 STORMWATER FOLLOW-UP INSP Approved Approved
04/13/2011 STORMWATER FOLLOW-UP INSP Continued Spoke to Steve with ESI about the appilcation rate for the Gollia Snot on remaining distrubed areas. We agreed to a rate of 137 gal/ AC for dust control. The erosion controls measures will remain in placed and be kept in good cond. The remaining AC to be treated is 15 arces. This will be placed on 4/20.
02/16/2011 STORMWATER FOLLOW-UP INSP Correction Required SWPPP controls not in place around the new stockpile of dirt from the Costco site, need to install controls
09/28/2010 STORMWATER FOLLOW-UP INSP Continued SPOKE WITH JAY. WILL MEET ON SITE EARLY 10/10.
08/30/2010 STORMWATER FOLLOW-UP INSP Continued RECEIVED PHONE CALL FROM COSTCO REP (425-313-6691) REGARDING STAUS OF COSTCO GRADING PERMIT. PLANS HAVE BEEN SUBMITTED HOWEVER THEY ARE WAITING TO PULL BOTH BUILDING AND GRADING PERMITS, UNTIL THE OVERALL GRADING IS NEARER COMPLETION. POSSIBLY OCT. HE WILL CALL WHEN PERMITS HAVE BEEN PULLED TO RELAY PERMIT #'S
08/19/2010 STORMWATER FOLLOW-UP INSP Continued SPOKE WITH JAY REGARDING TRACK-OUT ON KINO. THEY ARE CALLING SWEEPER OUT.
08/04/2010 STORMWATER FOLLOW-UP INSP Continued RIGHT-OF-WAY WORK BEING DONE OFF OF KINO. STABILIZED CONTROLS HAVE BEEN TEMP. REMOVED. SOME TRACK-OUT ON KINO DUE TO SITUATION.
06/23/2010 STORMWATER FOLLOW-UP INSP Continued WORK CONTINUES. NO CONCERNS AT THIS TIME.
06/10/2010 STORMWATER FOLLOW-UP INSP Continued DROVE SITE WITH JAY AND SITE SUPER TO DISCUSS STORMWATER CONTROLS. PRIMARY CONCERN IS THE S/W CORNER OF SITE NEAR EXISTING BASIN AND THE AMOUNT OF RUN-OFF THIS AREA WILL RECEIVE DURING MONSOON.
06/02/2010 STORMWATER FOLLOW-UP INSP Continued Met with Dan with Borderland on-site, V trench for storm controls are being installed told Dan that some temp settling ponds will be needed in a few areas. We will review placement when grading activities begin.