Inspection Status: Approved

Inspection History: GRADING - INTERMEDIATE

Permit Number - T10BU00083

Inspection Description - GRADING - INTERMEDIATE

Inspection Status - Approved

Date Description Inspector Results Comments
04/20/2011 GRADING - INTERMEDIATE Approved Final 2 bollards will be checked with building permit.T09Cm03304
04/13/2011 GRADING - INTERMEDIATE Continued Gave Jackson Dean super copy of as-built submittal to have bollards placed at HC parking stall. Bollards have been placed along at grade sidewalk as approved on as-built. Also discussed rate of appilcation for Gollia Snot on distrubed areas. this will be placed on 4/20.
03/15/2011 GRADING - INTERMEDIATE Continued PRELERLIMINARY PUNCH LIST. #1 CLEAN ALL BASINS #2 PROVID PROTECTION FOR STORMWATER FOR ALL OF PARKING LOT.#3 COMLET ALL WORK IN PARKING LOT.#4 INSALL ALL SIGNS AND STRIPING.#5PROVIDE STORM CLEANOUT COVERS NOT SEWER CLEANOUT COVERS.#6 COMPLET WALKING PATHS RAILING.#7 REPAIR ADA SIDEWALK ON WEST SIDE OF BUILDING. #8INSALL BIKE LOCKERS. #9 REMOVE ALL CONSTRUCTION PARTS AND TRASH AND EQUIPMENT.
03/14/2011 GRADING - INTERMEDIATE Continued WORKING ON PARKING LOT ALL AROUND BUILDING.
02/28/2011 GRADING - INTERMEDIATE Continued Paving began for parking lot, checked PAAL width and sidewalk width.
02/22/2011 GRADING - INTERMEDIATE Continued Checked parking area LS islands and PAAL width prior to paving also checked grades for GB.
02/16/2011 GRADING - INTERMEDIATE Correction Required Dirt was being removed from Costco site and dumped on Bridges site outside of SWPPP controls and approved grading limits, Asked contractor to stop the dirt haul until SWPPP controls and a revised plan are in place.
01/14/2011 GRADING - INTERMEDIATE Partial Approval Storm CB's poured without rebar per approved plans. Contractor has installed pipe along northside of parking lot and has three more CB's excavated and ready to form.
01/12/2011 GRADING - INTERMEDIATE Partial Approval Contractor has 3 Cb formed and ready for conc. no rebar present in CB looked for an approved plan onsite but was unable to locate one. Returned to office and found our approved plan set and the detail for CB on site does not have rebar, so approved to pour CB's as is in field.
12/29/2010 GRADING - INTERMEDIATE Continued Met with pipe contractor and discussed installation of pipe. Need to bed pipe on sides and bottom at D/2. 6" min over the top of pipe.
They will begin installing pipe on 12/30.