Inspection History Details
Inspection Status: Approved
Inspection History: GRADING - INTERMEDIATE
Permit Number - T10BU00083
Inspection Description - GRADING - INTERMEDIATE
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
04/20/2011 | GRADING - INTERMEDIATE | Approved | Final 2 bollards will be checked with building permit.T09Cm03304 | |
04/13/2011 | GRADING - INTERMEDIATE | Continued | Gave Jackson Dean super copy of as-built submittal to have bollards placed at HC parking stall. Bollards have been placed along at grade sidewalk as approved on as-built. Also discussed rate of appilcation for Gollia Snot on distrubed areas. this will be placed on 4/20. | |
03/15/2011 | GRADING - INTERMEDIATE | Continued | PRELERLIMINARY PUNCH LIST. #1 CLEAN ALL BASINS #2 PROVID PROTECTION FOR STORMWATER FOR ALL OF PARKING LOT.#3 COMLET ALL WORK IN PARKING LOT.#4 INSALL ALL SIGNS AND STRIPING.#5PROVIDE STORM CLEANOUT COVERS NOT SEWER CLEANOUT COVERS.#6 COMPLET WALKING PATHS RAILING.#7 REPAIR ADA SIDEWALK ON WEST SIDE OF BUILDING. #8INSALL BIKE LOCKERS. #9 REMOVE ALL CONSTRUCTION PARTS AND TRASH AND EQUIPMENT. | |
03/14/2011 | GRADING - INTERMEDIATE | Continued | WORKING ON PARKING LOT ALL AROUND BUILDING. | |
02/28/2011 | GRADING - INTERMEDIATE | Continued | Paving began for parking lot, checked PAAL width and sidewalk width. | |
02/22/2011 | GRADING - INTERMEDIATE | Continued | Checked parking area LS islands and PAAL width prior to paving also checked grades for GB. | |
02/16/2011 | GRADING - INTERMEDIATE | Correction Required | Dirt was being removed from Costco site and dumped on Bridges site outside of SWPPP controls and approved grading limits, Asked contractor to stop the dirt haul until SWPPP controls and a revised plan are in place. | |
01/14/2011 | GRADING - INTERMEDIATE | Partial Approval | Storm CB's poured without rebar per approved plans. Contractor has installed pipe along northside of parking lot and has three more CB's excavated and ready to form. | |
01/12/2011 | GRADING - INTERMEDIATE | Partial Approval | Contractor has 3 Cb formed and ready for conc. no rebar present in CB looked for an approved plan onsite but was unable to locate one. Returned to office and found our approved plan set and the detail for CB on site does not have rebar, so approved to pour CB's as is in field. | |
12/29/2010 | GRADING - INTERMEDIATE | Continued | Met with pipe contractor and discussed installation of pipe. Need to bed pipe on sides and bottom at D/2. 6" min over the top of pipe. They will begin installing pipe on 12/30. |