Inspection Status: Approved
Inspection History: ENGINEERING PRE-CONSTRUCTION
| Date |
Description |
Inspector |
Results |
Comments |
| 12/07/2010 |
ENGINEERING PRE-CONSTRUCTION |
|
Approved |
Held pre-con with Jackson Dean Construction today, talked about areas of inspection responsibility, also SWPPP copntrols and what is needed for final approval. Also discussed what we will inspect. |
| 05/25/2010 |
ENGINEERING PRE-CONSTRUCTION |
|
Partial Approval |
DROVE THROUGH THE SITE TO SEE WHAT IS EXPECTED TO HAPPEN WITH THIS PROJECT IN THE NEAR FUTURE. CREWS WORKING ON PREPARING TO INSTALL SOME OF THE STORMWATER CONTROLS. MALENA CARREON WILL BE WATCHING THIS SITE THROUGH ITS ENTIRETY. SEE THE COMMENTS ALSO POSTED ON GRADING PERMIT T10BU00084 BY MALENA CARREON OFR THIS SITE AND THE ADJACENT SITE ON 5/27/2010 |