Inspection History Details
Inspection Status: Approved
Inspection History: PLUMBING - GAS PRESSURE TEST
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/17/2009 | PLUMBING - GAS PRESSURE TEST | Approved | IVRS - Inspection :* 1) OK TO COVER PIPING |
|
| 11/10/2009 | PLUMBING - GAS PRESSURE TEST | Not ready for Inspection | IVRS - Inspection :* 1) PROVIDE PIPE TAPE PRIMER AND THEN TAP ALL TOOL MARKS AND FITTINGS UNDERGROUND TO ACHIEVE 40 MIL THICKNESS OF PIPE WRAP 2) REMOVE TAPE AT SINGLE TO DBL WALL VENT CONNECTOR AND EXTEND DBL WALL VENT TO 3' ABOVE TOP OF COOLER WHEN WITHIN 10' OF COOLER INTAKE WITH DBL WALL VENT PIPING 3) WATER HEATER TEMPERATURE AND PRESSURE RELIEF DEVICE SHALL GRAVITY DRAIN TO DAYLIGHT AND BE FUNCTIONAL OR BE INSTALLED PER PETITION OF APPEAL LEFT ON SITE 4) RETEST SYSTEM AFTER STEM #1 ABOVE AND HAVE TEST IN PLACE AT TIME OF INSPECTION |