Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit: T09PL00061

Parcel: 10512024E


Addresses:

4040 N ORACLE RD


Inspection Status: Approved

Inspection History: SITE - SEWER

Permit Number - T09PL00061

Inspection Description - SITE - SEWER

Inspection Status - Approved

Date Description Inspector Results Comments
08/25/2009 SITE - SEWER Approved IVRS - Inspection :*
07/21/2009 SITE - SEWER Partial Approval IVRS - Inspection :*
1) VACUUM TEST M.H. #1
2) MIRROR AND MANDRELL
07/20/2009 SITE - SEWER Not ready for Inspection IVRS - Inspection :*
06/01/2009 SITE - SEWER Partial Approval IVRS - Inspection :*
8" DIP EXTENDED TO MANHOLE #1 OK
BLDG. DRAIN EXTENDED TO MANHOLE #1
I'D LIKE TO SEE BASE POURED AND RINGS SET
05/21/2009 SITE - SEWER Partial Approval IVRS - Inspection :*
1) 8" D.I.P. INSTALLED FROM PROPERTY LINE CLEANOUT NORTH TWO HUNDRED FEET OK TO COVER, SUBJECT VERIFICATION OF GRADE AND TESTING
05/19/2009 SITE - SEWER Partial Approval 8" DIP INSTALLED FROM MANHOLE IN ROGER RD. TO PROPERTY LINE CLEANOUT OK -- VERIFICATION OF GRADE AND TEST AT A LATER DATE. OK TO COVER.

AFTER HRS. INSP. 2 HRS. TO BE PAID FROM ADOLFSON/PETERSON ACCT. $150.00
03/30/2009 SITE - SEWER Partial Approval IVRS - Inspection :*
03/30/2009 SITE - SEWER Not ready for Inspection IVRS - Inspection :*
NOT READY FOR INSPECTION
03/20/2009 SITE - SEWER Partial Approval AFTER HRS. INSP. TO BE BILLED TO
ADOLFSON PETERSON ACCT. - TWO HRS. $150.00

STREET CUT TO MANHOLE
TAPPED MANHOLE
INSTALL D.I.P
CONNECT TO D.I.P AT PROPERTY LINE
03/10/2009 SITE - SEWER Not ready for Inspection IVRS - Inspection :*
02/27/2009 SITE - SEWER Not ready for Inspection IVRS - Inspection :*
SPECIAL INSPECTION REQUESTED
BY JIM BECHTEL W/AP CONST.
SPECIAL BEFORE HRS. INSP. $150.00 TO BE
CHARGED TO AP CONST.
02/27/2009 SITE - SEWER Partial Approval IVRS - Inspection :*
02/18/2009 SITE - SEWER Not ready for Inspection IVRS - Inspection :*
NO NEW WORK TODAY
02/17/2009 SITE - SEWER Partial Approval IVRS - Inspection :*
MEETING WITH WESTLAND RESOURCES CONCERNING SEWER TAP AND TIE IN AT ORACLE
02/09/2009 SITE - SEWER Not ready for Inspection IVRS - Inspection :*
VENT NOT APPROVED, VENT TO RISE VERTICALLY TO ABOVE FLOWLINE BEFORE OFFSETTING HORIZONTALLY
USE DRAINAGE FITTINGS
02/06/2009 SITE - SEWER Partial Approval IVRS - Inspection :*
1. 4" RADIO SHACK AND 4" BASKIN ROBBINS
TIED INTO 6" SDR 35 W/TRACER OK
2. INTERCEPTOR INSTALLED OK. CUT IN A VENT
3. OK TO COVER 6" SDR35 TO P.O.C AT EXISTING 6" CLAY
02/02/2009 SITE - SEWER Not ready for Inspection WAITING FOR RFI INFORMATION ON BASKIN ROBBINS
01/22/2009 SITE - SEWER Partial Approval IVRS - Inspection :*
6" PVC FROM INTERCEPTOR (NOT SET) TO EXISTING C.O. 9233*01 AT BASKIN ROBBINS INSTALLED,
NOT CONNECTED TO CLEANOUT - CONTRACTOR HAS
SENT RFI CONCERNING AS BUILT CONDITION
01/21/2009 SITE - SEWER Partial Approval IVRS - Inspection :*
01/20/2009 SITE - SEWER Partial Approval IVRS - Inspection :*
MANHOLES #2 & #3 RINGS STACKED TODAY
01/16/2009 SITE - SEWER Partial Approval IVRS - Inspection :*
1 8" D.I.P FROM PROPERTY LINE TO MH#2 OK TO COVER SUBJECT TO VERIFICATION OF GRADE AND TEST AT A LATER DATE.
2. MANHOLE BASES #2 & #3 POURED TODAY
3. SDR35 FROM MH#2 TO MH#3 OK TO COVER SUBJECT TO VERIFICATION OF GRADE AND TEST AT A LATER DATE
4. D.I.P STUBBED OUT OF MANHOLE #3