Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

PRO is currently experiencing an outage. Some documents and records may not be available on PRO momentarily. We apologize for the inconvenience and are working to restore full access.

Permit: T09PL00061

Parcel: 10512024E


Addresses:

4040 N ORACLE RD

Inspection Status: Approved

Inspection History: SITE - SEWER

Date Description Inspector Results Comments
08/25/2009 SITE - SEWER Approved IVRS - Inspection :*
07/21/2009 SITE - SEWER Partial Approval IVRS - Inspection :*
1) VACUUM TEST M.H. #1
2) MIRROR AND MANDRELL
07/20/2009 SITE - SEWER Not ready for Inspection IVRS - Inspection :*
06/01/2009 SITE - SEWER Partial Approval IVRS - Inspection :*
8" DIP EXTENDED TO MANHOLE #1 OK
BLDG. DRAIN EXTENDED TO MANHOLE #1
I'D LIKE TO SEE BASE POURED AND RINGS SET
05/21/2009 SITE - SEWER Partial Approval IVRS - Inspection :*
1) 8" D.I.P. INSTALLED FROM PROPERTY LINE CLEANOUT NORTH TWO HUNDRED FEET OK TO COVER, SUBJECT VERIFICATION OF GRADE AND TESTING
05/19/2009 SITE - SEWER Partial Approval 8" DIP INSTALLED FROM MANHOLE IN ROGER RD. TO PROPERTY LINE CLEANOUT OK -- VERIFICATION OF GRADE AND TEST AT A LATER DATE. OK TO COVER.

AFTER HRS. INSP. 2 HRS. TO BE PAID FROM ADOLFSON/PETERSON ACCT. $150.00
03/30/2009 SITE - SEWER Partial Approval IVRS - Inspection :*
03/30/2009 SITE - SEWER Not ready for Inspection IVRS - Inspection :*
NOT READY FOR INSPECTION
03/20/2009 SITE - SEWER Partial Approval AFTER HRS. INSP. TO BE BILLED TO
ADOLFSON PETERSON ACCT. - TWO HRS. $150.00

STREET CUT TO MANHOLE
TAPPED MANHOLE
INSTALL D.I.P
CONNECT TO D.I.P AT PROPERTY LINE
03/10/2009 SITE - SEWER Not ready for Inspection IVRS - Inspection :*
02/27/2009 SITE - SEWER Not ready for Inspection IVRS - Inspection :*
SPECIAL INSPECTION REQUESTED
BY JIM BECHTEL W/AP CONST.
SPECIAL BEFORE HRS. INSP. $150.00 TO BE
CHARGED TO AP CONST.
02/27/2009 SITE - SEWER Partial Approval IVRS - Inspection :*
02/18/2009 SITE - SEWER Not ready for Inspection IVRS - Inspection :*
NO NEW WORK TODAY
02/17/2009 SITE - SEWER Partial Approval IVRS - Inspection :*
MEETING WITH WESTLAND RESOURCES CONCERNING SEWER TAP AND TIE IN AT ORACLE
02/09/2009 SITE - SEWER Not ready for Inspection IVRS - Inspection :*
VENT NOT APPROVED, VENT TO RISE VERTICALLY TO ABOVE FLOWLINE BEFORE OFFSETTING HORIZONTALLY
USE DRAINAGE FITTINGS
02/06/2009 SITE - SEWER Partial Approval IVRS - Inspection :*
1. 4" RADIO SHACK AND 4" BASKIN ROBBINS
TIED INTO 6" SDR 35 W/TRACER OK
2. INTERCEPTOR INSTALLED OK. CUT IN A VENT
3. OK TO COVER 6" SDR35 TO P.O.C AT EXISTING 6" CLAY
02/02/2009 SITE - SEWER Not ready for Inspection WAITING FOR RFI INFORMATION ON BASKIN ROBBINS
01/22/2009 SITE - SEWER Partial Approval IVRS - Inspection :*
6" PVC FROM INTERCEPTOR (NOT SET) TO EXISTING C.O. 9233*01 AT BASKIN ROBBINS INSTALLED,
NOT CONNECTED TO CLEANOUT - CONTRACTOR HAS
SENT RFI CONCERNING AS BUILT CONDITION
01/21/2009 SITE - SEWER Partial Approval IVRS - Inspection :*
01/20/2009 SITE - SEWER Partial Approval IVRS - Inspection :*
MANHOLES #2 & #3 RINGS STACKED TODAY
01/16/2009 SITE - SEWER Partial Approval IVRS - Inspection :*
1 8" D.I.P FROM PROPERTY LINE TO MH#2 OK TO COVER SUBJECT TO VERIFICATION OF GRADE AND TEST AT A LATER DATE.
2. MANHOLE BASES #2 & #3 POURED TODAY
3. SDR35 FROM MH#2 TO MH#3 OK TO COVER SUBJECT TO VERIFICATION OF GRADE AND TEST AT A LATER DATE
4. D.I.P STUBBED OUT OF MANHOLE #3