Inspection History Details
Inspection Status: Approved
Inspection History: MECHANICAL - FINAL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/09/2009 | MECHANICAL - FINAL | Approved | IVRS - Inspection :* | |
| 11/18/2009 | MECHANICAL - FINAL | Denied | IVRS - Inspection : See detailed listing on site.| 999* 1) SEE ITEMS DATED 10/01/09 |
|
| 11/13/2009 | MECHANICAL - FINAL | Denied | IVRS - Inspection : See detailed listing on site.| 999* 1) PROVIDE PROPER DESCRIPTION OF WORK, THIS IS NOT A REPLACEMENT SEE NOTE #4 DATED 10/01/09 2) 30 MIN. IS MAX LEAD TIME AVAILABLE |
|
| 11/12/2009 | MECHANICAL - FINAL | Not ready for Inspection | IVRS - Inspection :* | |
| 11/06/2009 | MECHANICAL - FINAL | Denied | IVRS - Inspection : See detailed listing on site.| 999* 1) CONTRACTOR TO BE ON SITE AT NEXT INSPECTION 2) ALL ITEMS LISTED ABOVE ALL TO BE COMPLETE OR REFEE WILL BE ADDED TO THIS PERMIT |
|
| 10/01/2009 | MECHANICAL - FINAL | Denied | IVRS - Inspection : See detailed listing on site.| 999* 1) ALL PVC TO HAVE PRIMERED JOINTS 2) ALL PVC TO BE PAINTED IF EXPOSED TO EXTERIOR 3) GAS PIPING NOT COMPLETE 4) PROVIDE PERMIT FOR NEW INSTALLATION OF GAS PACK INCLUDING TRUSS LOAD CALCS 5) PROVIDE ELECTRICAL PERMIT 6) PROVIDE PLUMBING GAS PERMIT 7) REMOVE ELECTRICAL DISCONNECT FROM UNIT 8) PROVIDE MIN. R-8 (2") INSULATION ON ALL EXTERIOR DUCT 9) SEAL ALL EXTERIOR DUCT JOINTS INCLUDING PITTSBURGH 10) SPLITER IN ELBOW HAS OPEN GAP BETWEEN SUPPLY AND RETURN 12) PROVIDE MINIMUM R-8 INSULATION ON ALL DUCT IN VENTED ATTIC |