Inspection Status: Approved
Inspection History: MECHANICAL - FINAL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/15/2009 | MECHANICAL - FINAL | Approved | IVRS - Inspection :* | |
| 05/20/2009 | MECHANICAL - FINAL | Denied | IVRS - Inspection : See detailed listing on site.| 999* 1. PROVIDE THE REQUIRED DRAWING APPROVED BY CITY OF TUCSON TO ALLOW A NEW ROOFTOP INSTALLATION 2. DESCRIPTION IS INCORRECT 3. A PACKAGE UNIT WAS NOT REPLACED 4. A NEW ELEC. CIRCUIT AND GAS LINE WAS ADDED 5. 2" INSULATION ON ROOFTOP DUCT IS OK 6. HOWEVER ALL LEADING EDGES OF INSULATION MUST BE PROTECTED FROM THE AIR FLOW FOR EXAMPLE AT THE RETURN AIR INTAKE ABOVE THE FILTER 7. I.D. CIRCUIT BREAKER |
|
| 04/20/2009 | MECHANICAL - FINAL | Denied | IVRS - Inspection : See detailed listing on site.| 999* 1. PROVIDE GFI SERVICE RECEPTACLE ON ROOF 2. PROVIDE SEDIMENT TRAP AT GAS PIPING 3. SEAL TITE CONNECTOR BROKEN 4. PROVIDE R-8 INSULATION ON ALL DUCT EXPOSED TO EXTERIOR 5. PROVIDE PROPER DESCRIPTION OF WORK 6. PROVIDE APPROVED ENGINEERED DRAWING FOR RTU HEAT PUMP |