Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Inspection History Details
Inspection Status: Approved
Inspection History: INSP - FOLLOW UP CODE ENFORCE
Case Number - T09DV03160
Inspection Description - INSP - FOLLOW UP CODE ENFORCE
Inspection Status - Approved
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/19/2014 | INSP - FOLLOW UP CODE ENFORCE | Approved | All the permit have been finaled when meeting with LeeRay. At this time the case will be closed. Violation Abated, Close Case. RV. | |
| 09/24/2013 | INSP - FOLLOW UP CODE ENFORCE | Approved | Met with the management and the buildings are almost done. The contractor is currently work on building #7 and should be calling for inspection. Will check in 45 days. RV. | |
| 03/28/2013 | INSP - FOLLOW UP CODE ENFORCE | Approved | Met with the management and the contractor on site. They are working on building #5 and should be done in 3-weeks. The building they will be doing next is building #6 after completed with building #5. Will check in 60 days. RV. | |
| 12/12/2012 | INSP - FOLLOW UP CODE ENFORCE | Approved | FU SHOWS WORK BEING DONE WITH PERMIT. FU 45 DAYS. | |
| 10/31/2012 | INSP - FOLLOW UP CODE ENFORCE | Approved | FU SHOWS WORK BEING DONE WITH PERMITS. FU 30 DAYS | |
| 09/19/2012 | INSP - FOLLOW UP CODE ENFORCE | Approved | SITE VISIST SHOWS NO WORK, CONTACT WILL BE MADE WITH OWNERS. FU 30 DAYS FOR PERMITS. | |
| 09/13/2012 | INSP - FOLLOW UP CODE ENFORCE | Approved | FU SHOWS NO ONE ON SITE. ALL WORK APEARS COMNPLETED. | |
| 07/13/2012 | INSP - FOLLOW UP CODE ENFORCE | Approved | FU SHOWS NO ONE ON SITE, RAIN DELAY. RESCHEDULE POUR. FU 20 JULY 12 | |
| 07/11/2012 | INSP - FOLLOW UP CODE ENFORCE | Approved | FU SHOWS BUILDING 9 STILL BEING WORKED ON. PERMIT IS IN ISSUED STATUS. BEAMS REPLACED, LANDINGS TO BE POURED ON 13 JULY 12. FU 13 JULY 12 | |
| 06/08/2012 | INSP - FOLLOW UP CODE ENFORCE | Approved | FU SHOWS WORK BEING DONE TO BUILDING 9. CONTACT MADE WITH TONY AND JOESPH FOR PERMTIS AND ALSO LEERAY HANLEY. PERMITS WILL STAY IN EXPIRED STATUS UNTIL THEY CALL FOR INSPECTIONS OK PER LEERAY H. FU 15 DAYS. | |
| 05/31/2012 | INSP - FOLLOW UP CODE ENFORCE | Approved | FU INSPECTION SHOWS BUILDING 8 COMPLETED. PHOTOS TAKEN, ALL WORK APPEARS TO BE DONE CORRECTLY. WILL CHECK PERMIT STATUS. BUILDING 9 VACANT WITH ALL BEAMS EXSPOSED & READY FOR REMOVAL AND REPLACEMENT. |
|
| 03/30/2012 | INSP - FOLLOW UP CODE ENFORCE | Approved | FU SHOWS WORK BEING DONE WITH PERMITS. FU 60 DAYS. | |
| 02/24/2012 | INSP - FOLLOW UP CODE ENFORCE | Approved | FU SHOWS WORK BEING DONE TO PERMIT. ALL BUILDING WITH WORK TO BE COMPLETED HAVE ACTIVE PERMITS,; BUILDINGS # 2 T10CMBU00179, #4 T10BU00181, #8 T10BU00185, #9 T10BU00186 ALL IN ISSUED STATUS. BUILDINGS #1,5,6,7,10,11 ALL WITHDRAWN OR EXSPIRED WITH NO BEAM REPLACEMENT TO BE COMPLETED. BUILDING #3 TI0BU00180 FINAL. FU 26 MAR 2012 |
|
| 01/18/2012 | INSP - FOLLOW UP CODE ENFORCE | Approved | FU SHOWS WORK BEING DONE TO BUILDING 8, PERMIT I ISSUED STATUS. FU 24 FEB12 |
|
| 12/16/2011 | INSP - FOLLOW UP CODE ENFORCE | Approved | FU INSPECTION SHOWS SHROING STILL IN PLACE, PERMITS SECURED FOR SHORING. ALL BUILDING HAVE PERMITS FOR BEAM REPLACEMENT THAT ARE EXPIRED, EXCEPT #3 IS IN FINAL STATUS. # 1: NO SHORING, NO BEAM REPLACEMENT REQUIRED. #2: SHORING COMPLETED, WORK TO BE DONE, #3 COMPLIANCE. #4 SHORING COMPLETED, WORK TO BE DONE, #5 NO SHORING, NO BEAM REPLACEMENT REQUIRED. #6 SHORING COMPLETE, WORK TO BE DONE. #7 SHORING COMPLETE, WORK TO BE DONE. #8 BUILDING IS UNOCCUPIED, SHORING COMPLETED WORK TO BE DONE. #9 SHORING COMPLETED, WORK TO BE DONE. #10 NO SHORING, NO BEAM REPLACEMENT REQUIRED. #11 NO SHORING, NO BEAM REPLACEMENT REQUIRED. CONTACT MADE WITH TONY AT KOWAISKI CONSTRUCTION, I INFORMED HIM IF THEY WORK WITHOUT A ACTIVE PERMIT THE OWNER WILL BE CITED. THIS INFO HAS ALSO BEEN GIVEN TO LEIGH MASSEY (480-5050-9330) REP FOR THE OWNERS. I RECEIVED A CALL FROM BILL KRANE (602-757-4729) FROM KOWAISKI CONSTRUCTION STATING THAT THE PERMIT FOR #8 HAS BEEN RENEWED. I INFORMED LEIGH MASSEY THAT WE WILL NEED A LETTER FROM JOHN BARRY FROM COPPER CREEK ENG. WITH HIS STAMP STATING THE BUILDINGS 1,5,10,&11 WILL NOT REQUIRE SHORING SO THE PERMIT CAN BE CLOSED. BUILDINGS 2,6,7,8,& 9 NEED TO BE IN ISSUED STATUS. FU 30 DAYS. FOR LETTER. |
|
| 08/06/2009 | INSP - FOLLOW UP CODE ENFORCE | Approved | BUILDINGS SHORED ARE2,3,4,8,7,9 WITH PERMITS. I CONTACTED JOHN BERRY AND HE WILL EMAIL ME REPORT WITHIN 1 WEEK. REPORT WILL SHOW THE PROCEDURE TO REPAIR DEFECTS FU 10 SEPT 09 |
|
| 06/23/2009 | INSP - FOLLOW UP CODE ENFORCE | Approved | MET WITH ENGINEER AND CONTRACTOR ON SITE TO DISCUSS BUILDINGS. NOV RECEIVED AND GIVEN TO ENGINEER IS MAKING ARRANGEMENTA FOR SHORING AND BRACING FU 6/30/09 |