Case: T09DV03085

Parcel: 117062950


Addresses:

422 E 9TH ST


Inspection Status: Approved

Inspection History: INSP - FOLLOW UP CODE ENFORCE

Case Number - T09DV03085

Inspection Description - INSP - FOLLOW UP CODE ENFORCE

Inspection Status - Approved

Date Description Inspector Results Comments
03/28/2012 INSP - FOLLOW UP CODE ENFORCE Approved PERMIT T11CM01581 IS FINAL AS OF 2-08-2012
CLOSE CASE
09/26/2011 INSP - FOLLOW UP CODE ENFORCE Approved PERMIT T11CM01581 IS IN ISSUED STATUS, COURT CASE WAS CLOSED. SCHEDULE A FOLLOW UP INSPECTION FOR 3-19-2012
08/18/2011 INSP - FOLLOW UP CODE ENFORCE Approved SPOKE TO OWNER PRIOR TO COURT HE STATED ARRANGEMENTS WITH ARCHITECT HAVE BEEN MADE AND THE PLAN CORRECTIONS WILL CONTINUE. I DID ADVISE THE CORT OF THE CASE STATUS AND ASKED FOR A 30 DAY CONTINUANCE. THE JUDGE APPROVED AND SCHEDULED A COMPLIANCE HEARING FOR SEPTEMBER 26, 2011 AT 0930.
03/08/2011 INSP - FOLLOW UP CODE ENFORCE Approved NO ACTIVITY IN PERMITS PLUS. NO PROGRESS OR CONTACT FROM OWNER OR ARCHITECT. WILL ISSUE CITATION.
02/23/2011 INSP - FOLLOW UP CODE ENFORCE Approved ARCHITECT EMAIL THAT THE PROJECT HAS STOPPED DUE TO LACK OF PAYMENT. SITE VISIT KNOCKED ON DOOR NO ANSWER LEFT BUSINESS CARD.
01/12/2011 INSP - FOLLOW UP CODE ENFORCE Approved LEFT CARD ON DOOR, WILL CALL ARCHITECT,
SCHEDULE FOLLOW UP INSPECTION 30 DAYS OUT
12/03/2010 INSP - FOLLOW UP CODE ENFORCE Approved RECEIVED POSITIVE EMAIL WILL GRANT EXTENSION 30 DAYS
10/21/2010 INSP - FOLLOW UP CODE ENFORCE Approved WILL CHANGE FOR FOLLOW UP DATE TO NOV 01, 2010
09/09/2010 INSP - FOLLOW UP CODE ENFORCE Approved SCHEDULED FOLLOW UP INSPECTION FOR OCT 21,2010
06/04/2010 INSP - FOLLOW UP CODE ENFORCE Approved SCHEDULED A 60 DAY FOLLOW UP INSPECTION.
03/30/2010 INSP - FOLLOW UP CODE ENFORCE Approved RECEIVED EMAIL FROM ARCHITECT STATING THE PROJECT HAS CHANGED DIRECTION NOW THE OWNERS WANT TO CHANGE THE USE TO RESIDENTIAL WHICH ACCORDING TO THE ARCHITECT WILL REQUIRE MORE TIME, WILL REVIEW CASE IN 30 DAYS.
02/11/2010 INSP - FOLLOW UP CODE ENFORCE Approved MET WITH SUPERVISOR AND ADVISED OF THE ARCHITECTS EMAIL STATING THAT THE PROJECT WAS ON HOLD BUT NOW IS MOVING FORWARD. NEED ENGINEERING FROM THE PLUMBING CONTRACTOR.
SUPERVISOR STATED UP SCHEDULE FOLLOW UP FOR 30 DAYS OUT
01/06/2010 INSP - FOLLOW UP CODE ENFORCE Approved MEETING WITH SUPERVISOR AND OWNER, OWNER EXPRESS CONCERNS ON THE COMPLIANT AND RIGHT OF ENTRY. OWNER DID STATE THAT SHE WAS GOING TO CONTINUE WITH WORK REQUIRED BUT DID STATE THE COST OF THE ELECTRICAL WAS VERY EXPENSIVE. I GRANTED ANOTHER 30 DAYS TO OBTAIN THE PERMIT.
09/15/2009 INSP - FOLLOW UP CODE ENFORCE Approved OWNER IS REQUESTING EXTENSION AND HAS HIRED BOB VINT ARCHITECT. I DID RECEIVED EMAIL FROM BOB WHICH STATES
MS. ALENE FLETCHER HAS RETAINED MY FIRM TO
> DOCUMENT CONDITIONS AT THE APARTMENT SHE OWNS @ 422. E. 9TH ST.,
> AND TO PREPARE A SET OF PERMIT DRAWINGS FOR SUBMITTAL AND REVIEW BY
> DEVELOPMENT SERVICES IN RESPONSE TO THE ZONING VIOLATION ISSUED RE. THIS
> PROPERTY. WORK IS IN PROGRESS IN PREPARING OUR SUBMITTAL. LAST WEDNESDAY
> 9/8 I ARRANGED FOR TANQUE VERDE ELECTRIC TO INSPECT THE ELECTRICAL
> SYSTEM. WE WILL NEED ANOTHER 2 TO 3 WEEKS TO ASSEMBLE COMPLETE PLANS. I
> AM WRITING AT THE REQUEST OF MS FLETCHER TO REQUEST AN EXTENSION
> OF THE 9/15/09 DEADLINE. THANK YOU FOR YOUR ATTENTION,
> BOB VINT
> ARCHITECT

30 DAY EXTENSION GRANTED