Inspection Status: Approved
Inspection History: INSP - FOLLOW UP CODE ENFORCE
| Date |
Description |
Inspector |
Results |
Comments |
| 01/14/2010 |
INSP - FOLLOW UP CODE ENFORCE |
|
Approved |
Violations abated. Permit has been finaled, T09CM01270 on 1/13/2010. Close case. |
| 12/23/2009 |
INSP - FOLLOW UP CODE ENFORCE |
|
Approved |
Talked to tenant and he will be moving out. Final will be called in by next week. Has to pour stoop on storage room door before calling in final. Will check in 10 days. |
| 11/30/2009 |
INSP - FOLLOW UP CODE ENFORCE |
|
Approved |
Met Charles on site and will be calling for finals by next week. All issues have been repaired. Will check in 30 days. |
| 07/14/2009 |
INSP - FOLLOW UP CODE ENFORCE |
|
Approved |
CHECKED PERMITS PLUS AND PERMIT HAS BEEN ISSUED, T09CM01270, ON 7-6-09 WITH INSPECTION DONE ON 7-8-09 AND NEEDS SOME CORRECTION. WILL FOLLOW UP IN 45 DAYS. |
| 05/26/2009 |
INSP - FOLLOW UP CODE ENFORCE |
|
Approved |
Met with tenant who performed some of the work. Drawing completed and submitted for approval. He has the plans back and making the corrections. Yard has been cleaned in front and not completed in the back. Went over the requirements for permits. He is going to add a section of fencing inside main property line where a fence is already installed and no review required. Will follow-up in 45 days. |