Inspection Status: Approved

Inspection History: EXCAVATION/LAYOUT REBAR & ZON

Permit Number - T09CM03305

Inspection Description - EXCAVATION/LAYOUT REBAR & ZON

Inspection Status - Approved

Date Description Inspector Results Comments
03/03/2011 EXCAVATION/LAYOUT REBAR & ZON Approved IVRS - Inspection :*
1) SPOKE WITH JIM
02/24/2011 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) SOUTH TANK DRIVE SLAB; CURBS AND VALLEY GUTTER
02/11/2011 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) GAS STATION CANOPY SLAB AND SERVICE ISLAND (6)-DETAILS #1,2 AND 34
2) PLEASE BILL JACKSON/DEAN ACCOUNT $165.00 FOR AFTER HOURS INSPECTION ON THIS DATE
01/07/2011 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) REBAR OK PEDNING ENGINEERING STAMPED RFI REGARDING CONDUITS IN STEM/FOOTING
2) NEED CITY APPROVED FIELD SET
12/30/2010 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) 8 CANOPY COLUMN FOOTINGS AS PER DETAILS #1 &^ 4 PAGE S-1
2) POUR TO BE DETERMINED BY SPECIAL INSPECTOR AS PER GUIDE LINES FOR COLD WEATHER POURS
3) JACKSON-DEAN ACCOUNT TO BE BILLED $165.00 FOR SCHEDULED APPOINTMENT INFO
12/16/2010 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) 8 DEAD MONO POURS FOR GAS TANK HOLDOWNS OK