Inspection Status: Approved
Inspection History: EXCAVATION/LAYOUT REBAR & ZON
Permit Number - T09CM03305
Inspection Description - EXCAVATION/LAYOUT REBAR & ZON
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
03/03/2011 | EXCAVATION/LAYOUT REBAR & ZON | Approved | IVRS - Inspection :* 1) SPOKE WITH JIM |
|
02/24/2011 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1) SOUTH TANK DRIVE SLAB; CURBS AND VALLEY GUTTER |
|
02/11/2011 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1) GAS STATION CANOPY SLAB AND SERVICE ISLAND (6)-DETAILS #1,2 AND 34 2) PLEASE BILL JACKSON/DEAN ACCOUNT $165.00 FOR AFTER HOURS INSPECTION ON THIS DATE |
|
01/07/2011 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1) REBAR OK PEDNING ENGINEERING STAMPED RFI REGARDING CONDUITS IN STEM/FOOTING 2) NEED CITY APPROVED FIELD SET |
|
12/30/2010 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1) 8 CANOPY COLUMN FOOTINGS AS PER DETAILS #1 &^ 4 PAGE S-1 2) POUR TO BE DETERMINED BY SPECIAL INSPECTOR AS PER GUIDE LINES FOR COLD WEATHER POURS 3) JACKSON-DEAN ACCOUNT TO BE BILLED $165.00 FOR SCHEDULED APPOINTMENT INFO |
|
12/16/2010 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1) 8 DEAD MONO POURS FOR GAS TANK HOLDOWNS OK |