Inspection History Details
Inspection Status: Approved
Inspection History: PLUMBING - INTERMEDIATE
Permit Number - T09CM03304
Inspection Description - PLUMBING - INTERMEDIATE
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
04/11/2011 | PLUMBING - INTERMEDIATE | Approved | IVRS - Inspection :* | |
04/08/2011 | PLUMBING - INTERMEDIATE | Not ready for Inspection | IVRS - Inspection :* | |
04/07/2011 | PLUMBING - INTERMEDIATE | Not ready for Inspection | IVRS - Inspection :* 1) SEE NOTES FROM 3/21/11 INSPECTION 2) SUPPORT AND SECURE ALL PIPING |
|
03/31/2011 | PLUMBING - INTERMEDIATE | Not ready for Inspection | IVRS - Inspection :* 1) COMPLETE TESTING ON AWV AT MEZZANINE AND MEAT PREP |
|
03/21/2011 | PLUMBING - INTERMEDIATE | Not ready for Inspection | 1. PROVIDE DWV TESTING ON REMAINDER OF DWV SYSTEM AT FRESH LINE AND SECOND LEVEL MECH. MEZZANINE. NOTE: PLEASE SEE ALL DETAILS SHOWN ON PLUMBING PAGES AND INSTALL PER APPROVED PLANS OR PROVIDE SEALED LETTER FROM ENGINEER DELETING THEM. | |
03/17/2011 | PLUMBING - INTERMEDIATE | Partial Approval | IVRS - Inspection :* 1) WATER DIST. TIRE SHOP OK PENDING ROOF HOSE BIB |
|
03/15/2011 | PLUMBING - INTERMEDIATE | Not ready for Inspection | IVRS - Inspection :* | |
03/09/2011 | PLUMBING - INTERMEDIATE | Partial Approval | IN WALL DWV AND WATER FOR TRAP STANDARD AT TIRE SHOP OK | |
03/03/2011 | PLUMBING - INTERMEDIATE | Partial Approval | IVRS - Inspection :* 1) RD PER INITIALS ON P-1.1 ON SOUTH WATER TEST 2) WATER TEST 3" DWV THRU ROOF 8.1 AND ? |
|
03/02/2011 | PLUMBING - INTERMEDIATE | Partial Approval | IVRS - Inspection :* | |
03/01/2011 | PLUMBING - INTERMEDIATE | Partial Approval | 1. DWV WATER TEST THRU ROOF. FOOD SERVICE OK. WATER AND NITROGEN DITRIBUTION FOOD SERVICE OK. 2. 1 1/2' GAS FROM ABOVE CEILING TO 3 3/4' OUTLETS FOR PIZZA OVEN 10 PSI TEST. | |
02/25/2011 | PLUMBING - INTERMEDIATE | Partial Approval | IVRS - Inspection :* 1) DWV THRU ROOF BAKERY AREA WITH WATER PIPING IN WALL TO STUB UPS OVER MEZZAINE |
|
02/17/2011 | PLUMBING - INTERMEDIATE | Partial Approval | IVRS - Inspection :* | |
02/14/2011 | PLUMBING - INTERMEDIATE | Not ready for Inspection | IVRS - Inspection :* | |
02/14/2011 | PLUMBING - INTERMEDIATE | Partial Approval | IN WALL PLPING IN PHOTO CENTER &OPTIAL ONLY INWALL OK ROOF IN WALL ONLY | |
02/12/2011 | PLUMBING - INTERMEDIATE | Partial Approval | 1. DWV TEST TO 3' VENT 90 DEGREE VERTICAL OK 2. WATER DISTRIBUTION TEDT STUBBED OUT TEO ONE INCH HW, 2' CW, ALL FOR RECEIVING RESTROOM AREA. | |
02/11/2011 | PLUMBING - INTERMEDIATE | Partial Approval | IVRS - Inspection :* | |
02/11/2011 | PLUMBING - INTERMEDIATE | Denied | 1. TEST TO BE IN PLACE AND FREE OF LEAKS. ALL PIPING TO BE SUPPORTED CORRECTLY. | |
02/10/2011 | PLUMBING - INTERMEDIATE | Partial Approval | 1. BREAK ROOM FIRST AND SECOND FLOOR IN WALL PIPING FOR L S SINKS OK (ONLY) | |
02/09/2011 | PLUMBING - INTERMEDIATE | Partial Approval | IVRS - Inspection :*ABOVE CEILING FROM WATER HEATER ROOM ON WEST TO RESTROOM & DEMO ROOMSIDE TEST OK (ONLY0 | |
02/08/2011 | PLUMBING - INTERMEDIATE | Not ready for Inspection | IVRS - Inspection :* | |
02/07/2011 | PLUMBING - INTERMEDIATE | Partial Approval | IVRS - Inspection :* PARTIAL APPROVAL- 1-INSTALL WATER PIPING SIZE PER APPRV PLAN CALL FOR 3/4 DROPS IN WALLS, 1/2 INSTALL TEST ON 1/2 OK FOR DEMO AREA. PHARMACY (ONLY) 2-SOUTHWEST SET OF ROOF DRAIN TEST OF "J" LINE |
|
02/04/2011 | PLUMBING - INTERMEDIATE | Not ready for Inspection | IVRS - Inspection :* | |
02/03/2011 | PLUMBING - INTERMEDIATE | Not ready for Inspection | IVRS - Inspection :* | |
02/02/2011 | PLUMBING - INTERMEDIATE | Partial Approval | IVRS - Inspection :* | |
02/01/2011 | PLUMBING - INTERMEDIATE | Partial Approval | IVRS - Inspection :* |