Inspection Status: Approved

Inspection History: PLUMBING - ROUGH, SOIL

Date Description Inspector Results Comments
03/03/2011 PLUMBING - ROUGH, SOIL Approved IVRS - Inspection :*
02/01/2011 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection :*
1. FLOOR SING ROUGH-SOIL FOR EAST SIDE PUMP ROOM TEST OK AND ROOF DRAIN
2. DEMO ROOM PROVIDE SUPPORT IN WALLS FOR PVC, COMPLETE ALL COPPER
01/20/2011 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection :*PER HIGHLIGHT ON 1.1
01/19/2011 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection :*
01/18/2011 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection :*
1) TEST ON ROOF DRAIN STUB UP TO TEST TEE ON WEST SIDE OF BLDG
2) TEST ON PIPING FOR GREASE INTERCEPTOR ON SOUTH WEST SIDE
01/13/2011 PLUMBING - ROUGH, SOIL Not ready for Inspection IVRS - Inspection :*
1) WEST SIDE OF BLDG HCS OK
01/12/2011 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection :*
1) LOADING DOCK TRENCH DRAIN INSTALLED
01/11/2011 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection :*
1) ROUGH SOIL INSIDE BLDG SLAB OK
2) PRE-SLAB INSIDE BLDG SLAB OK
3) WEST IN SLAB ROOF DRAIN
01/06/2011 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection :*
1) ROUGH SOIL FOR FOOD SERVICE AREA OK (ONLY)
01/03/2011 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection :*
1) CONTINUATION OF 6" GW FROM 118 THRU C/L F PER INITIAL AND HIGHLIGHT PAGE P2.3 WATER TEST TO ABOVE CLEANOUT HEIGHT WITH 3' VENT FROM CW AND V
12/30/2010 PLUMBING - ROUGH, SOIL Not ready for Inspection IVRS - Inspection :*
12/29/2010 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection :*
1) OPTICAL EXAM SINKS
2) SOUTHEAST SIDE FOR BLDG TEST OK FOR SITE SEWER
3) PROVIDE BUSHING AT TIE INS
12/28/2010 PLUMBING - ROUGH, SOIL Not ready for Inspection IVRS - Inspection :*
1. RECIEVING AREA RESTROOM #124 #123 AND PLUMBING SOUTH OF LINE ON EAST END FOR P[ROCESS
2. FLOOR SINK AT WEST END ON LINE AND NORTH OF FLOOR
12/27/2010 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection :*
1) P-2.3 HIGHLIGHT OK
12/23/2010 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection :*
1) PER HIGHLIGHT P.1.1, P2.1 AND P2.3
12/22/2010 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection :*
1) OIL AND WATER SEPERATOR TST OK (ONLY) FOR GAS STATION
12/21/2010 PLUMBING - ROUGH, SOIL Not ready for Inspection IVRS - Inspection :*
12/17/2010 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection :*
1) 3" TYPE K STUB IN 10' AND 6' UP
2) 80 PSI TEST OK
12/14/2010 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection :*
1) MENS RESTROOM #143, JANITOR 144, HEARING CENTER 136, 145 ELECTRICAL, WOMENS RESTROOM 142, RESTROOM 134 ON PAGE P-2.1 ROUGH SOIL OK (ONLY)
12/07/2010 PLUMBING - ROUGH, SOIL Not ready for Inspection IVRS - Inspection :*
1) PRE-CON MEETING WITH CONTRACTOR