Inspection History: REINFORCED MASONRY PRE-GROUT
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/30/2009 | REINFORCED MASONRY PRE-GROUT | Approved | IVRS - Inspection :* 1) PLANTERS COMPLETE |
|
| 12/09/2009 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* 1) ELEVATOR AND ADJACENT ROOMS TOP OUT 2) TERRACON SPECIAL INSPECTED |
|
| 12/08/2009 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* 1) ELEVATOR AND ADJACENT ROOMS 18' TO 22'-4" 2) TERRACON SPECIAL INSPECTED |
|
| 12/07/2009 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* 1) 4TH LIFT 13' TO 18' 2) TERRACON COMPLIANT INSPECTION |
|
| 12/03/2009 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* 1. 3RD LIFT ELEVATOR & 2 ADJACENT ROOMS 2. OK WITH COMPLIANT SPECIAL INSPECTION |
|
| 12/02/2009 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* | |
| 12/01/2009 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* 1) 1ST LIFT AT ELEVATOR, EQUIPMENT ROOM, UTILITES ROOM 2) PROVIDE RFI FOR 2 BAR INSTEAD OF #3 REBAR AT INTERSECTION 3) TERRACON INSPECTED PARTIAL 2ND LIFT INCLUDING LT1 & LT2 LINTELS, RFJ FOR 2 CLIP AT INTERSECTING WALLS, ELECTOR & EQUIP RMS |