Inspection History Details
Inspection Status: Approved
Inspection History: EXCAVATION/LAYOUT REBAR & ZON
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/11/2010 | EXCAVATION/LAYOUT REBAR & ZON | Approved | IVRS - Inspection :* | |
| 02/16/2010 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1) EAST AND WEST STAIRS FOOTINGS |
|
| 02/08/2010 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1) NORTH STAIR COLUMN FOOTINGS |
|
| 02/05/2010 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | IVRS - Inspection :* 1) FOOTING NOT DONE |
|
| 02/04/2010 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1) SOG N & NE EXT SIDEWALK TOE DOWNS OK 2) SPECIAL INSPECTED AND STAIR WELL FOOTING |
|
| 02/01/2010 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* SW ENTRY SLAB HAS BEEN SPECIAL INSPECTED |
|
| 01/20/2010 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* | |
| 01/06/2010 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1) POUR BACK AT EXTERIOR WALL COLUMNS OK |
|
| 12/23/2009 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1) 8-F3 EXT COLUMN FOOTINGS, 3 PLANTER FOOTINGS, 1-F2 SCREEN WALL FOOTING AND RESTRAINING WALL FOOTING 2) TERRACON SPECIAL INSPECTED |
|
| 11/10/2009 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1) ELEVATOR PIT, UTILITIES ROOM AND EQUIPMENT ROOM |
|
| 11/06/2009 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | 1) 4 INTERIOR FS FOOTINGS 2) BLDG PERIMETER F1,F2,F3,F4 FOOTINGS 3) TERRACON SPECIAL INSPECTED 4) PROVIDE SPECIAL INSPECTION CERTS SIGNED BY BLDG OFFICIAL |