Inspection Status: Approved
Inspection History: MECHANICAL - HYDRONIC PIPING
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/26/2011 | MECHANICAL - HYDRONIC PIPING | Approved | IVRS - Inspection :* | |
| 11/18/2010 | MECHANICAL - HYDRONIC PIPING | Partial Approval | IVRS - Inspection :* 100 PSI TEST ON REMANINING STEAM, CHILLED WATER, HEATING, HOT WATER, CONDENSATE RECOVERY. OK TO INSULATE. |
|
| 10/28/2010 | MECHANICAL - HYDRONIC PIPING | Partial Approval | IVRS - Inspection :* | |
| 10/15/2010 | MECHANICAL - HYDRONIC PIPING | Partial Approval | IVRS - Inspection :* 100 PSI HYDRO TEST ON REHEAT WATER PIPING AREA A MAIN CORRIDOR OK TO INSULATE |
|
| 10/14/2010 | MECHANICAL - HYDRONIC PIPING | Partial Approval | IVRS - Inspection :* HYDRONIC PIPING IS REQUIRED TO HAVE MIN 100 PSI HYDROSTATIC TEST |
|
| 10/12/2010 | MECHANICAL - HYDRONIC PIPING | Partial Approval | IVRS - Inspection :* 1) TEST ON HVAC HOT AND COLD PIPING ACROSS ROOF TO PENTHOUSE. OK TO INSULATE |
|
| 09/07/2010 | MECHANICAL - HYDRONIC PIPING | Partial Approval | IVRS - Inspection :* | |
| 08/11/2010 | MECHANICAL - HYDRONIC PIPING | Partial Approval | IVRS - Inspection :* |