Inspection History Details
Inspection Status: Approved
Inspection History: PLUMBING - PROGRESS
Permit Number - T09CM02836
Inspection Description - PLUMBING - PROGRESS
Inspection Status - Approved
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/23/2011 | PLUMBING - PROGRESS | Approved | IVRS - Inspection :* | |
| 06/21/2011 | PLUMBING - PROGRESS | Partial Approval | IVRS - Inspection :* 1) AREA D SINK CORRECTIONS COMPLETE |
|
| 06/16/2011 | PLUMBING - PROGRESS | Partial Approval | IVRS - Inspection :* | |
| 06/13/2011 | PLUMBING - PROGRESS | Partial Approval | IVRS - Inspection :* | |
| 05/26/2011 | PLUMBING - PROGRESS | Partial Approval | IVRS - Inspection :* 1) 4 INSTALLERS MAKING TIE IN TO ROOM OUTLETS WEST, AREA B |
|
| 05/17/2011 | PLUMBING - PROGRESS | Partial Approval | IVRS - Inspection :* 1) DOMESTIC PIPING K.T. 10597 AND WORK ROOM 10598 OK 2) MED GAS OUTLETS WITH TEST, WEST SIDE OF AREA B |
|
| 04/27/2011 | PLUMBING - PROGRESS | Partial Approval | IVRS - Inspection :* | |
| 04/25/2011 | PLUMBING - PROGRESS | Partial Approval | IVRS - Inspection :* | |
| 04/20/2011 | PLUMBING - PROGRESS | Partial Approval | IVRS - Inspection :* | |
| 04/18/2011 | PLUMBING - PROGRESS | Partial Approval | IVRS - Inspection :* | |
| 04/13/2011 | PLUMBING - PROGRESS | Partial Approval | IVRS - Inspection :* 1) MED GAS PROGRESS AND SHOWER DIVERTERS OK, CALL FOR DAILY PROGRESS INSPECTIONS |
|
| 03/22/2011 | PLUMBING - PROGRESS | Partial Approval | IVRS - Inspection :* 1) IRRIGATION SYSTEM IS DIRECTLY CONNECTED TO A HOSE BIBB WITHOUT APPROVED BACKFLOW PREVENTION (AT OLD JOB TRAILER LOCATION). PLEASE CORRECT THIS UNLAWFUL CROSS CONNECTION 2) MOTHER/BABY 5-SHOWER VALVE REPLACEMENT OK |
|
| 02/25/2011 | PLUMBING - PROGRESS | Partial Approval | IVRS - Inspection :* 1) PROVIDE APPROVED DRAINAGE TUBING WITHOUT RESTRICTIONS ON FILTER BLEED DOWN. CLAMP DRAIN HOSE CONNECTIONS STRAINER |
|
| 02/02/2011 | PLUMBING - PROGRESS | Not ready for Inspection | we will use plumbing progress for the remainder of this project | |
| 01/31/2011 | PLUMBING - PROGRESS | Partial Approval | IVRS - Inspection :* | |
| 01/26/2011 | PLUMBING - PROGRESS | Partial Approval | IVRS - Inspection :* | |
| 01/11/2011 | PLUMBING - PROGRESS | Not ready for Inspection | IVRS - Inspection :* 1) MET WITH VALERIE ROBINSON, SHIRLEY AND FRED REGARDING A SOLUTION FOR THE EXTERNAL OVERFLOW TUBING ON SINKS AND LAVS 2) WILL REMOVE UNLISTED FITTINGS |
|
| 12/07/2010 | PLUMBING - PROGRESS | Denied | IVRS - Inspection : See detailed listing on site.| 999* 1) THE OVER FLOW DRAIN ASSEMBLY CONNECTED TO THE UNLISTED SINKS AND LAVS, INSTALLED IN PATIENT ROOMS DO NOT APPEAR TO MEET THE REQUIREMENTS PRESCRIBED IN UPC SECTIONS 401.1 AND 301.1.3 THEY APPEAR TO PRESENT A POTENTIAL BACTERIA CONTAMINATION HAZARD 2) PROVIDE THE LISTING AS REQUIRED BY UPC 301.1.1 OR REMOVE THIS ASSEMBLY 3) BRIAN T WITH TMC, JASON WITH LLOYD AND FRED FROM R E ? |
|
| 11/23/2010 | PLUMBING - PROGRESS | Partial Approval | IVRS - Inspection :* | |
| 11/09/2010 | PLUMBING - PROGRESS | Denied | IVRS - Inspection : See detailed listing on site.| 999* 1) KEEP OPEN DRAIN PIPES PLUGGED DURING CONSTRUCTION |
|
| 11/03/2010 | PLUMBING - PROGRESS | Not ready for Inspection | IVRS - Inspection :* | |
| 11/02/2010 | PLUMBING - PROGRESS | Not ready for Inspection | IVRS - Inspection :* | |
| 09/22/2010 | PLUMBING - PROGRESS | Not ready for Inspection | IVRS - Inspection :* 1) CALL FOR DAILY MED GAS INSPECTION |
|
| 08/16/2010 | PLUMBING - PROGRESS | Partial Approval | IVRS - Inspection :* | |
| 07/30/2010 | PLUMBING - PROGRESS | Denied | IVRS - Inspection : See detailed listing on site.| 999* 1) CONTRACTORS NEED TO CORDINATE DEMO TO KEEP ALL OPEN DRAINS CAPPED! SECOND WARNING, SEE NOTES FROM 2/24 DO NOT LET THIS BECOME A PROBLEM |
|
| 07/15/2010 | PLUMBING - PROGRESS | Partial Approval | IVRS - Inspection :* | |
| 07/08/2010 | PLUMBING - PROGRESS | Not ready for Inspection | IVRS - Inspection :* | |
| 05/19/2010 | PLUMBING - PROGRESS | Partial Approval | IVRS - Inspection :* 1) CAP ALL OPENINGS TO PREVENT THE ESCAPE OF SEWER GASES |
|
| 05/06/2010 | PLUMBING - PROGRESS | Partial Approval | IVRS - Inspection :* |