Inspection Status: Approved
Inspection History: PLUMBING - ROUGH, SOIL
Permit Number - T09CM02836
Inspection Description - PLUMBING - ROUGH, SOIL
Inspection Status - Approved
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/24/2010 | PLUMBING - ROUGH, SOIL | Approved | IVRS - Inspection :* | |
| 08/23/2010 | PLUMBING - ROUGH, SOIL | Denied | IVRS - Inspection : See detailed listing on site.| 999* |
|
| 08/20/2010 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* 1) SOIL PIPING AREA C, MATCH LINE TO COL. 4 OK 2) INSTALL TEST FITTINGS ? 3) RW MAN HOLE INSIDE BLDG 4) VAC TEST WITNESSED BY MATT WITH RBV |
|
| 08/17/2010 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* 801.2.3 INDIRECT PIPING MAY NOT COMBINE |
|
| 08/16/2010 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* | |
| 08/11/2010 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* | |
| 08/10/2010 | PLUMBING - ROUGH, SOIL | Not ready for Inspection | IVRS - Inspection :* | |
| 08/09/2010 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* | |
| 08/05/2010 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* | |
| 07/30/2010 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* 1) STAFF TR AND SINKS, CONFERENCE ROOM AND CHILD ? BABY OK |
|
| 07/29/2010 | PLUMBING - ROUGH, SOIL | Not ready for Inspection | IVRS - Inspection :* | |
| 07/23/2010 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* 1) AREA 'A' SOIL PIPE WITH TST THRU ABOVE SLAB TEST FITTINGS OK, ALL EXCEPT 15052 |
|
| 07/09/2010 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* 1) EAST OF COL. PC, SOIL PIPEW WITH TEST THRU CLEANOUT FITTINGS OK TO COVER |
|
| 07/08/2010 | PLUMBING - ROUGH, SOIL | Not ready for Inspection | IVRS - Inspection :* | |
| 06/28/2010 | PLUMBING - ROUGH, SOIL | Not ready for Inspection | IVRS - Inspection :* | |
| 06/23/2010 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* 1) PUBLIC TRS 15059 & 60 ALSO MS 58 OK 2) NOTE: WILL NEED TO SEAL SHOWER DRAINS PER UPC INSTALLATION STANDARD #4 WHICH REQUIRES UTILIZATION OF DRAIN CLAMPING RING AND WEEP HOLES |
|
| 06/21/2010 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* 1) SOIL PIPE CORRECTION FOR TR10129A OK TO COVER 2) INSTALL WRAPS FOR PRE-SLAB INSPECTION |
|
| 06/18/2010 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* 1) TR 130A AND 129A OK 2) 129 EXISTING PIPING REQUIRES CORRECTION (LEAKING) |
|
| 06/16/2010 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* TRS 10132 & 10133A OK |
|
| 06/15/2010 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* | |
| 05/19/2010 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* 1) 8" SCHEDULE 80 PVC SEWER REPLACEMENT AND CONNECTIONS TO EXISTING AS SPECIFIED OK |
|
| 05/18/2010 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* SCH 80 MAIN REPLACEMENT W/ WATER TEST OK |
|
| 05/17/2010 | PLUMBING - ROUGH, SOIL | Not ready for Inspection | IVRS - Inspection :* PROVIDE WATER TEST, AND REDLINE CHANGES. LETTER ON SITE FOR CHANGES FROM THOMAS SPARS PE |
|
| 05/10/2010 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* 1) PROVIDE ENGINEER APPROVAL FOR ANY CHANGES |