Inspection Status: Approved

Inspection History: PLUMBING - INTERMEDIATE

Date Description Inspector Results Comments
04/13/2010 PLUMBING - INTERMEDIATE Approved IVRS - Inspection :*
1) CLOSET FLANGES OK
04/09/2010 PLUMBING - INTERMEDIATE Not ready for Inspection IVRS - Inspection :*
03/22/2010 PLUMBING - INTERMEDIATE Partial Approval IVRS - Inspection :*
03/22/2010 PLUMBING - INTERMEDIATE Partial Approval IN WALL PIPING OK TO COVER
ABV COILING IN HARD LIDS OK RECALL AFTER COILING QRID
RECALL 3035 FOR FLANGES INSP AND PLAN REVISIONS.
03/19/2010 PLUMBING - INTERMEDIATE Partial Approval IVRS - Inspection :*
1) WALLS OK AT ALL DOMESTIC PIPING
2) PROVIDE REVISIONS AND ABV CEILING INSP
03/18/2010 PLUMBING - INTERMEDIATE Partial Approval IVRS - Inspection :*
1) FHA STRAPS
2) ISOLATION OF PEX
3) 150 PSI ON AIR AND 02
03/17/2010 PLUMBING - INTERMEDIATE Not ready for Inspection IVRS - Inspection :*
1) WATER SUPPLY TO HUMIDIFIERS MAY REQUIRE BACKFLOW PROTECTION IF UNITS DO NOT HAVE A LISTING FOR BACKFLOW
03/12/2010 PLUMBING - INTERMEDIATE Partial Approval IVRS - Inspection :*
1) WATER DISTRIBUTION IN WALL WITH INSULATION OK
2) OVERHEAD REQUIRES INSULATION
3) NEED SHOWER VALVE INSTALL WITH SHOWER PAN LINER AND TEST PRIOR TO TILE
4) NEED TO SEE R.O. AND SOFT WATER SYSTEMS
03/10/2010 PLUMBING - INTERMEDIATE Partial Approval IVRS - Inspection :*
1) TEST ON YARD WATER OK
2) DWV TEST OK
03/09/2010 PLUMBING - INTERMEDIATE Not ready for Inspection IVRS - Inspection :*
03/08/2010 PLUMBING - INTERMEDIATE Partial Approval IVRS - Inspection :*
1) EXT. WALLS EXCEPT AT WATER CLOSET VENT
03/05/2010 PLUMBING - INTERMEDIATE Partial Approval IVRS - Inspection :*
03/04/2010 PLUMBING - INTERMEDIATE Not ready for Inspection IVRS - Inspection :*
1) PROTECT PASSING THRU STUCCO
2) YOU MAY NOT CONNECT A DRAIN TO A CLOSET BEND
BELOW SLAB CONSTRUCTION OK ' ' CHANGES OK SUBJECT TO PLAN REVISION
DWV HAS BEEN TOASTED TO A POINT ABOVE SLAB CLEAN OUT TOGS.
3) REMOVE DAMAGED PVC, DO NOT USE DISCOLORED OR OTHER WISE DAMAGED MATERIALS, ALSO SUPPORTS, SWEEPS AND TRAP ARM SIZES
4) PLAN SPECS INDICATE CONTINOUS INSULATION WITH SHEET METAL SADDLES
02/23/2010 PLUMBING - INTERMEDIATE Not ready for Inspection IVRS - Inspection :*
02/22/2010 PLUMBING - INTERMEDIATE Not ready for Inspection IVRS - Inspection :*
02/04/2010 PLUMBING - INTERMEDIATE Not ready for Inspection IVRS - Inspection :*
1) WD PIPING BELOW SLAB FOR ? OK
2) OK TO ROCK CEILING
01/26/2010 PLUMBING - INTERMEDIATE Not ready for Inspection IVRS - Inspection :*
1) REMOVE VENTS WITH COUPLINGS IN CONCELAED LOCATION, OR LEAVE EXPOSED UNTIL AFTER TEST