Inspection History Details
Inspection Status: Approved
Inspection History: EXCAVATION/LAYOUT REBAR & ZON
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/16/2010 | EXCAVATION/LAYOUT REBAR & ZON | Approved | IVRS - Inspection :* | |
| 03/04/2010 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1) GENERATOR FOOTINGS AS PER RFI (SK8, 2/8/10) SIWTH GEAR SCREEN WALLS OK TO POUR FOOTINGS |
|
| 12/10/2009 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1) CONTINOUS FOOTINGS (F1 & F5) AND (F2 & F3 ; COLUMN FOOTINGS |
|