Inspection History Details
Inspection Status: Approved
Inspection History: PLUMBING - GAS PRESSURE TEST
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/30/2009 | PLUMBING - GAS PRESSURE TEST | Approved | ||
| 10/09/2009 | PLUMBING - GAS PRESSURE TEST | Denied | IVRS - Inspection : See detailed listing on site.| 999* |
|
| 09/09/2009 | PLUMBING - GAS PRESSURE TEST | Denied | IVRS - Inspection : See detailed listing on site.| 999* DENIED - 8:20 NO ACCESS HAVE LIC. ELECTRICIAN, PLUMBER AND MECH. CONTRACTOR VERIFY IN WRITING ON COMPANY LETTERHEAD THAT ALL TRADES ARE TO CURRENT CODE - COMPLY WITH PREVIOUS REJECTION. |
|
| 08/21/2009 | PLUMBING - GAS PRESSURE TEST | Denied | IVRS - Inspection : See detailed listing on site.| 999* |