Inspection History Details
Inspection Status: Approved
Inspection History: BUILDING - FINAL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/04/2009 | BUILDING - FINAL | Approved | IVRS - Inspection :* 1) CORRECTIONS HAVE BEEN MADE |
|
| 08/20/2009 | BUILDING - FINAL | Denied | IVRS - Inspection : See detailed listing on site.| 999* |
|
| 08/07/2009 | BUILDING - FINAL | Not ready for Inspection | IVRS - Inspection :* 1) PROVIDE AN APROVED DRAIN PIPE FOR PRESSURE REILEF ON ROOF TO AVOID SCALDING 2) TEMPERATURE AND PRESSURE RELIEF AT HEATER IS REQUIRED TO GRAVITY DRAIN TO DAY LIGHT OR PROVIDE A PETITION OF APPEAL FOR ALTERNATE METHOD OF TEMPERATURE AND PRESSURE RELIEF WITH CORRECT INSTALLATION ON SITE 3) EXPANSION TANK IS TO HEAVY TO BE UNSUPPORTED, PROVIDE SUPPORT |