| 10/27/2009 | EXCAVATION/LAYOUT REBAR & ZON | Approved | IVRS - Inspection :* 1) MENU BOARD, SPEAKER POST, CLEARANCE BAR CAISSON FOOTINGS; DETAILS 331,32,30-OK TO POUR FOOTINGS |
|
| 10/20/2009 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1) 5 LIGHT POLE FOOTINGS; DETAIL #25, PAGE S1.3 SCREEN WALL FOOTING; DETAIL #26, PAGE S1.3-OK TO POUR PROGRESS AREAS |
|
| 10/10/2009 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1) NORTH AND WEST SCREEN WALL FOOTINGS; TRASH ENCLOSURE FOOTINGS AS PER CITY OF TUCSON SPECS-OK TO POUR PROGRESS AREAS 2) AFTER HOURS INSPECTION CHECK #02784 FOR $150.00 JOHNSON BANK |
|
| 10/06/2009 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1) CONTINOUSE FOOTINGS; HOLDOWN PLATES, DETAIL #23 PAGE S1.3 REQUIRES 1/2" METAL TO BE CHANGED FROM 1/4" TO 1/2"-OK TO POUR AFTER CONFIRMATION OF PLATE CHANGE 2) AFTER HOURS INSPECTION CHECK #02772 FOR $300 PLUMBING AND STRUCTURAL INSPECTIONS |