Inspection Status: Approved
Inspection History: MECHANICAL - ABOVE CEILING
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/27/2009 | MECHANICAL - ABOVE CEILING | Approved | IVRS - Inspection :* 1) 1ST AND 2ND FLOOR PRODUCTION AREA OK FOR TILES, MECH ONLY |
|
| 08/21/2009 | MECHANICAL - ABOVE CEILING | Partial Approval | IVRS - Inspection :* 1) OK FOR TILES IN LOBBY, BREAK ROOM AND TESTING AREA |
|
| 08/19/2009 | MECHANICAL - ABOVE CEILING | Not ready for Inspection | IVRS - Inspection :* 1) INSTALL FLEX PER PLANS ON ADDENDUM FROM ENGINEER DATED 8/18/09 MEL FILE #09-010 |
|
| 08/17/2009 | MECHANICAL - ABOVE CEILING | Partial Approval | IVRS - Inspection :* 1) OK TO BUILD CHASE AROUND EXISTING DUCT BOTH FLOORS PRODUCTION AREA AND SOFFIT ALONG EAST WALL 1ST FLOOR PRODUCTION AREA |
|
| 08/12/2009 | MECHANICAL - ABOVE CEILING | Partial Approval | IVRS - Inspection :* 1) FLEX DUCT NOT TO EXCEED 5' PER 16.A MECH SPECS M5.0 2) ALL SPIRAL JOINTS TO BE MADE WITH SPIRAL MATE OR EQUAL PER 4.C. MECH SPECS AT M5.0 3) PROVIDE CURB INSULATION PER DETAIL 1 M3.0 4) PROVIDE MINIMUM 3" COLLARS AT REGISTERS WHERE FLEX DUCT IS DIRECTLY ATTACHED 5) H.E. TAPS ARE TO HAVE FULL SIZE TAP INTO DUCT ROUND HOLES THE PIPE DIAMETER NOT ACCEPTABLE 6) INSTALL VOLUMN DAMPERS PER PLANS 7) SEAL H.E. TAPS PER SPECS |