Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit: T09CM00841

Parcel: 13606002C


Addresses:

8800 E 22ND ST 02


Inspection Status: Approved

Inspection History: EXCAVATION/LAYOUT REBAR & ZON

Permit Number - T09CM00841

Inspection Description - EXCAVATION/LAYOUT REBAR & ZON

Inspection Status - Approved

Date Description Inspector Results Comments
08/07/2009 EXCAVATION/LAYOUT REBAR & ZON Approved IVRS - Inspection :*
1) 5 CAISSON LIGHT POLE FOOTINGS-OK TO POUR PROGRESS AREAS
08/06/2009 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) SOUTH PARKING LOT 5 AT CAISSON LIGHT POLE FOOTINGS-RFI DATED 5/21/09
06/17/2009 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
BLDG. PRE-SLAB @ LOCKER RM. AREA ON EAST
END OF BLDG. @ GRID 7.2 TO 8/A TO F.2 - OK
06/09/2009 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
MAIN BLDG. MONO POUR OF STEM WALLS/PRE-SLAB @
1 TO 7.2/A TO K.8 - OK SPECIAL INSPECTION PERFORMED
06/08/2009 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
CONTINUOUS & COLUMN FOOTINGS STEEL REINFORCEMENT @ GRID LINE A/4 TO 6.5 -- OK
06/04/2009 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
BLDG. PERIMETER AND INTERIOR CONTINUOUS FOOTING AND COLUMN FOOTING EXCEPT 2 #F-3 COLUMN FOOTINGS @ GRID A/5 & 6 AND 1 F4 @ A/4 ALONG W/CONTINUOUS F-2 FOOTING BETWEEN THEM @ LINE A LEFT OUT FOR ACCESS DURING POUR -- OK TO POUR -- SPECIAL INSPECTION PERFORMED BY GRENIER ENGINEERING