Permit: T09CM00748

Parcel: 12112056C


Addresses:

5151 E SPEEDWAY BL

Inspection Status: Approved

Inspection History: BUILDING - PROGRESS

Date Description Inspector Results Comments
02/03/2010 BUILDING - PROGRESS Approved
10/29/2009 BUILDING - PROGRESS Partial Approval IVRS - Inspection :*
1) 16 MASONRY COLUMNS (WRAPS) TOPPED OUT AT 12' 8" OK TO GROUT AND CAP
10/28/2009 BUILDING - PROGRESS Partial Approval PRE GROUT 3RD LIFT-16 CMU COLUMN WRAPS AT 8' 8"-12' 8" OK TO GROUT
10/27/2009 BUILDING - PROGRESS Partial Approval IVRS - Inspection :*
1) 16 MASONRY COLUMN WRAPS 4' 8"- 8' 8" OK TO GROUT PROGRESS AREAS
10/14/2009 BUILDING - PROGRESS Partial Approval IVRS - Inspection :*
1) 16 COLUMN MASONRY WRAPS AT 54" OK TO GROUT PROGRESS AREAS