Inspection History Details
Inspection Status: Approved
Inspection History: EXCAVATION/LAYOUT REBAR & ZON
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/26/2009 | EXCAVATION/LAYOUT REBAR & ZON | Approved | IVRS - Inspection :* CONTINUOUS FOOTINGS AS PER DETAILS #102, 103; COLUMN FOOTINGS F1, F2, F3, F4 AS PER SCHEDULE OK TO POUR FOOTINGS - ENSURE ALL TRASH IS REMOVED FROM FOOTINGS BEFORE POURING |
|
| 05/22/2009 | EXCAVATION/LAYOUT REBAR & ZON | Cancelled | CANCELLED PER CONTRACTOR BOB SMITH #429-3845 | |
| 05/22/2009 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | IVRS - Inspection :* CONTRACTOR CANCELED (PER JOANN) |
|
| 05/21/2009 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | IVRS - Inspection :* CONTRACTOR CANCELED - RAINED OUT |