Permit: T09CM00318

Parcel: 13814457C


Addresses:

180 W VALENCIA RD A

Inspection Status: Approved

Inspection History: EXCAVATION/LAYOUT REBAR & ZON

Date Description Inspector Results Comments
06/26/2009 EXCAVATION/LAYOUT REBAR & ZON Approved IVRS - Inspection :*
1) GRENIER SPECIAL INSPECTED
06/25/2009 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1. POST FOOTINGS OK TO POUR
2. PIER FOOTING
05/07/2009 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
6 - COLUMN FOOTINGS ON BLDG. "A"
05/01/2009 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1. BLDG. D FOOTINGS POURED WITHOUT INSPECTION ALONG WITH BLDG. E - PROVIDE SPECIAL INSPECTION
2. ANY MORE FOOTINGS POURED WITHOUT C.O.T INSPECTION WILL HAVE TO BE RE-DONE
04/14/2009 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) BLDG E EXTERIOR LAYOUT/REBAR-PARTIAL-BLDG E EXTERIOR COLUMN AND PIER FOOTINGS DETAILS #101, 102 SPECIAL INSPECTED