Inspection History Details
Inspection Status: Partial Approval
Inspection History: MECHANICAL - INTERMEDIATE
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/08/2012 | MECHANICAL - INTERMEDIATE | Partial Approval | ||
| 01/13/2012 | MECHANICAL - INTERMEDIATE | Partial Approval | IVRS - Inspection :* 1) ROOM 101 OK FOR SHEETROCK 2) WILL CHECK CONDENSATE ON FINAL |
|
| 02/04/2011 | MECHANICAL - INTERMEDIATE | Partial Approval | ALL BUT ALTERNATE 4 WAS COMPLETED ON THIS DATE. APPROVAL CHANGED TO PARTIAL TO REINSPECT WHEN ALT 4 IS DONE. | |
| 09/29/2010 | MECHANICAL - INTERMEDIATE | Partial Approval | IVRS - Inspection :* | |
| 01/20/2010 | MECHANICAL - INTERMEDIATE | Partial Approval | IVRS - Inspection :* 1) CONDENSATE IN WALL OK TO COVER 2) RELOCATE LONG UNISTRUT TO END OF FAN COIL TO ALLOW ACCESS 3) ACCESS OPENING MINIMUM 20 X 30 BUT LARGE ENOUGH TO REMOVE EQUIPMENT 4) 9" SPIRAL DUCT NEEDS R8 INSULATION 5) CONFIRMED SEALED JOINTS |