Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit: T09CM00249

Parcel: 13707045F


Addresses:

4975 S LIBERTY AV


Inspection Status: Approved

Inspection History: REINFORCED MASONRY PRE-GROUT

Permit Number - T09CM00249

Inspection Description - REINFORCED MASONRY PRE-GROUT

Inspection Status - Approved

Date Description Inspector Results Comments
11/04/2010 REINFORCED MASONRY PRE-GROUT Approved IVRS - Inspection :*
10/28/2010 REINFORCED MASONRY PRE-GROUT Not ready for Inspection IVRS - Inspection :*
08/24/2010 REINFORCED MASONRY PRE-GROUT Partial Approval IVRS - Inspection :*
1) TRASH ENCLOSURE CMU WALLS TOP OUT OK
08/19/2010 REINFORCED MASONRY PRE-GROUT Partial Approval IVRS - Inspection :*
1) ELEVATOR SHAFT TOPPED OUT AT 25'-20' OK TO GROUT PROGRESS
08/18/2010 REINFORCED MASONRY PRE-GROUT Partial Approval IVRS - Inspection :*
CMU WALLS @ ELEVATOR SHAFT FROM 20 "0" TO 24 "0" AFFE OK TO GROUT
08/17/2010 REINFORCED MASONRY PRE-GROUT Partial Approval IVRS - Inspection :*
EMV WALLS @ ELEVATOR SHAFT FROM 16"0" TOZO
AFFE OK TO GROUT
08/16/2010 REINFORCED MASONRY PRE-GROUT Partial Approval IVRS - Inspection :*
ELEVATOR SHAFT TO 16' AFFE 4TH LIFT #5 - OK
08/12/2010 REINFORCED MASONRY PRE-GROUT Partial Approval IVRS - Inspection :*
1) PARTIAL TO 12'-4TH LIFT ABOVE FINISH FLOOR WITH COMPLAINT SPECIAL INSPECTION OK TO GROUT
08/11/2010 REINFORCED MASONRY PRE-GROUT Partial Approval IVRS - Inspection :*
1) 3RD LIFT OK WITH SPECIAL INSPECTION
2) INSTALL GUARD RAILS ON SCAFOLD AND PROVIDE LADDER
08/10/2010 REINFORCED MASONRY PRE-GROUT Partial Approval IVRS - Inspection :*
1) 2ND LIFT ELEVATOR SPECIAL INSPECTED
07/28/2010 REINFORCED MASONRY PRE-GROUT Partial Approval IVRS - Inspection :*
1) 1ST LIFT ELEVATION
2) SPEEDIE SPECIAL INSPECTED

1) CANCELLED PER CONTRACTOR

1) RAKE WALLS TOP OUT EAST SIDE LINE 4, E-5.8 TO 7, E-4 TO 5
2) SPECIAL INSPECTED

1) NEED POWER TO OFFICE AREA
2) NEED FIRE C OF O

1) GABLE ENDS REBAR IN PLACE LEDGER BOLTS NOT IN PLACE WAITING ON CLARIFICATION
2) OK TO GROUT 2 PEAK CELLS
3) NEED LEDGER BOLTS WITHIN 12" OF END

1) PROPERLY PLUMB AND DRAIN FIXTURES IN MECH ROOM (BACKFLOW AND DRAIN CONNECTIONS)
2) WORKING CLEARANCE REQUIRED AT ELECTRIC PANEL-RELOCATE WATER HEATER
3) USE LISTED DRAIN CONNECTORS UNDER LAV

1) FLOOR PLAN NEEDS TO BE CORRECTED
2) CAULK LINE AT WALL AND WATER CLOSETS AT FLOOR
3) REPAIR WIRE AT WATER HEATER

1) 3 COLUMN FOOTINGS OK TO POUR

1) NOTE: NEW A/C UNIT TO REPLACE OLD UNIT-CHECK BEFORE FINAL

1) OK SHEETROCK

1) NEED ELECTRIC FINAL

1) OK TO SET TILES THROUGHOUT

1) OK TO SET CEILING TILES

1) GLENN ST PEDESTRIAN BRIDGE-#4 REBAR AT 6" X 12" THROUGHOUT-OK TO POUR BRIDGE SLAB

1) CLIPS AND SHEATHING IN PLACE-OK TO STUCCO

1) ENSURE VANITY LIGHT FIXTURE IS IN PLACE PER PLANS, PAGE E-1

1) BOTH WALLS

1) BOTH WALLS

1) CLIPS AND STRAPS IN PLACE; SHEAR SHEATHING IN PLACE-OK TO COVER
2) NOTE: THIS SITE IS LOT #6 NOT LOT #11

1) GRADE BEAMS #1 THRU 9; C,D,E OK TO POUR PROGRESS AREAS

1) GL-#27 & 28; DETAILS #1,6.2.1 AT 5,6.2.2 FRAMING AND ROOF NAILING-OK TO DRY IN PROGRESS AREA

1) CONTRACTOR CANCELLED

1) PHASE II TOWER PROGRESS

1) PHASE II PROGRESS

1) PHASE II WEST WALL

1) GROUT ABOVE BEAM

1) BLOCK 3 SIDES ON MECH

1) 2ND LIFT OK

1) INCOMPLETE

1) 3RD LIFT OK

1) GL 1-2/B-H 2ND & 3RD FLOOR WELDS

1) PROGRESS AREA

1) LAV IN WOMENS RESTROOM NEEDS TO BE 34" MAX IN HEIGHT PER PLAN SHEET A3.1
2) TOILET IN WOMENS RESTROOM SHALL BE 18" TO CENTER OF WATER CLOSET PER PLAN SHEET A3.1

1) INFO ONLY

1) NEED SIGNAGE AT RESTROOM
2) NEED PLUMBING FINAL AND C OF O FIRE APPROVAL PRIOR TO THIS INSPECTION

1) NEED PLUMBING FINAL