Inspection History Details
Inspection Status: Approved
Inspection History: ELECTRIC - FINAL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/20/2009 | ELECTRIC - FINAL | Approved | IVRS - Inspection :* | |
| 04/15/2009 | ELECTRIC - FINAL | Denied | IVRS - Inspection : See detailed listing on site.| 999* 1. RECEPT FOR SERVICING AC UNIT TO BE GFI PROTECTED AND BOX SECURED TO BUILDING. SEAL OPEN KNOCK OUT 2. STRAP SEAL TIGHT WITHIN 12" OF CONNECTIONS 3. PROPERLY IDENTIFY EQUIPMENT GROUND TO CONDENSING UNIT BONDING JUMPER TO JUNCTION BOX TO BE #10 4. INSTALL GASKET ON LB COVER 5. SEAL OPEN KNOCKOUTS JUNCTION BOXES ABOVE CEILING 6. REPAIR/REPLACE DAMAGED ROMEX ABOVE DROP CEILING 7. INSTALL BREAKER LISTED FOR USE IN CUTLER HAMMER SERVICE PANEL 8. IT APPEARS THAT YOU CANNOT ENTER TOP OF SERVICE PANEL BECAUSE OF INSTALLED BARRIER. ENTER BELOW TOP SECTION. 9. HAVE 30 AMP CIRCUIT TO CONDENSING UNIT SIZE ALL CONDUCTORS PROPERLY. |