Inspection Status: Approved
Inspection History: GRADING - INTERMEDIATE
| Date |
Description |
Inspector |
Results |
Comments |
| 04/18/2011 |
GRADING - INTERMEDIATE |
|
Approved |
Approved |
| 04/11/2011 |
GRADING - INTERMEDIATE |
|
Continued |
Contraactor placing DG over all exposed areas of site, and finishing site work |
| 03/30/2011 |
GRADING - INTERMEDIATE |
|
Continued |
NO CONCERN AT THIS TIME. |
| 03/25/2011 |
GRADING - INTERMEDIATE |
|
Continued |
GOT WITH CONTRACTOR ABOUT CHECKING GRADING ON CONCERN AT THIS TIME. |
| 03/08/2011 |
GRADING - INTERMEDIATE |
|
Continued |
DRIVEWAY ON EAST SIDE PER PLAN SO FAR. |
| 01/03/2011 |
GRADING - INTERMEDIATE |
|
Partial Approval |
OK to backfill 12 PVC stormpipe from canopy area to basin, also OK to backfill 12 cmp PIPE BETWEEN BASINS. |