Inspection History Details
Inspection Status: Approved
Inspection History: GRADING - INTERMEDIATE
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/06/2010 | GRADING - INTERMEDIATE | Approved | ||
| 09/29/2010 | GRADING - INTERMEDIATE | Continued | CONTRACTOR PAVING FRONT SECTION OF PARKING AREA, WILL INSPECT AFTER PAVING COMPLETED. NO STORM WATER CONCERNS AT THIS TIME |
|
| 09/27/2010 | GRADING - INTERMEDIATE | Continued | SOME SITE WORK COMPLETED, NO CONCERNS. NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME. ENSURE PEDESTRIAN ACCESS WAY IS COMPLIANT WITH ANSI. ENSURE 6" WATER HARVESTING AREAS ARE INSTALLED PER PLAN | |
| 09/13/2010 | GRADING - INTERMEDIATE | Continued | SITE WORK BEING ACCOMPLISHED. CHANGE TO PED ACCESS AT CROSSING NEAR ENTRANCE DUE TO >2% CROSS SLOPE. CONTRACTOR WILL USE SOUTH PED ACCESS AS ADA ACCESS TO ROW. SOME CURBING COMPLETED, PAVING IN TWO WEEKS. NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME | |
| 08/23/2010 | GRADING - INTERMEDIATE | Continued | NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME. A STABILIZED CONSTRUCTION ENTRANCE HAS BEEN INSTALLED, AND THE SUROUNDING AREA IS SWEPT ROUTINELY. NO SITE WORK TAKING PLACE AS OF TODAY |