Inspection History: FIRE SPKLR - UG, PIPING, HYDRO
Permit Number - T09BU01796
Inspection Description - FIRE SPKLR - UG, PIPING, HYDRO
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
05/07/2010 | FIRE SPKLR - UG, PIPING, HYDRO | Approved | Approved 5/7/10 | |
05/07/2010 | FIRE SPKLR - UG, PIPING, HYDRO | Partial Approval | OKAY TO COVER FROM TEE TO FIRST VALVE BEFORE TURN ON THE WEST SIDE | |
05/06/2010 | FIRE SPKLR - UG, PIPING, HYDRO | Partial Approval | Approved Dip section still need 200 psi test and flush. Ok to cover. | |
05/06/2010 | FIRE SPKLR - UG, PIPING, HYDRO | Partial Approval | 200 PSI OK STILL NEEDS FLUSH | |
03/11/2010 | FIRE SPKLR - UG, PIPING, HYDRO | Partial Approval | 200 PSI TEST FOR 2 HOURS, FROM TIE IN EAST TO TIE IN ON WEST END FOR FUTURE HOOK UP TO FIRE LINE AND 15 FOOT PIPE OFF OF TEE. STILL NEEDS TO BE FLUSHED. | |
03/10/2010 | FIRE SPKLR - UG, PIPING, HYDRO | Partial Approval | OKAY TO COVER FROM TIE IN PONITE ON THE EASTSIDE TO 167 FEET TO TEE AND 15 FOOT PIPE FOR SPRINKLER SYSTEM. |