Inspection History: GRADING - INTERMEDIATE
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/30/2010 | GRADING - INTERMEDIATE | Approved | AS-BUILT DRAWINGS WILL BE REQUIRED TO BE SUBMITTED AND APPROVED PRIOR TO SCHEDULING THE FINAL GRADING INSPECTION. | |
| 07/02/2010 | GRADING - INTERMEDIATE | Continued | 1) ELEVATION CHANGES WERE MADE IN PARKING LOT IN ORDER TO STAY IN COMPLIANCE W/ HC PARKING AND ACCESS WAY MINIMUM AND MAXIMUM SLOPES REQUIRED. 2) SWALE WILL BE CONSTRUCTED APPROXIMATELY 30' IN FROM THE NORTH SIDE OF LOT PROPERTY LINE, IN ORDER TO ALLOW STORM WATER TO DRAIN AWAY FROM THE FOUNDATION OF THE ADJACENT BLDG. 3) GROUTED ROCK RIP RAP WILL BE INSTALLED ALONG UP-SIDE OF NEW SIDEWALK AND AT OUTLET OF PARKING AREA SWALE. 4) ALL CHANGES MADE TO THE ORIGINAL APPROVED PLAN WILL BE SHOW ON AN AS-BUILT PLAN AND SUBMITTED TO THE COT FOR ARCHIVING. 5) SWEEP UP TRACKED SOIL OFF OF ADJACENT PUBLIC ROADWAY. |
|
| 06/29/2010 | GRADING - INTERMEDIATE | Continued | PLANS HAVE BEEN REVISED TO SHOW NEW SIDEWALK ACCESS FROM THE ROW TO THE BLDG THAT MEETS THE REQUIRED SLOPE. IN ACCORDANCE WITH THE SUPERINTENDENT, THE ENG OF RECORD STATED THAT THERE WAS NO NEED FOR A SCUPPER ALONG THE NW CORNER OF SITE. SURFACE DRAINAGE WILL SHEET FLOW DOWN DRIVEWAY ACCESS POINTS. |
|
| 06/23/2010 | GRADING - INTERMEDIATE | Continued | Spoke to Craig with Barker today regarding the sidewalk and HC location to building, could not install per approved plan and meet HC standards, they angled sidewalk to ROW, told craig he needs a revised site plan. Also told him he needs to address storm discharge at NW corner of parking with his engineer. May need a scupper threw the sidewalk to convey water. |