Inspection Status: Approved
Inspection History: ENGINEERING PRE-CONSTRUCTION
| Date |
Description |
Inspector |
Results |
Comments |
| 12/10/2010 |
ENGINEERING PRE-CONSTRUCTION |
|
Approved |
|
| 11/18/2010 |
ENGINEERING PRE-CONSTRUCTION |
|
Partial Approval |
MET WITH THE CONTRACTOR ON-SITE AND LOOKED OVER WHAT THEY HAVE BEEN DOING SINCE THE PREVIOUS SITE VISIT BY MIKE RUSSO. THEY HAVE CONSTRUCTION STARTED OF ALL THREE UNITS, APPROXIMATELY 50% OF THE SITE WORK IS COMPLETE AT THIS TIME. A PRE-CON PACKET MAYBE GIVEN TO THE CONTRACTOR FOR THEIR CONTACT INFORMATION, BUT THE SITE DOES NOT REQUIRE A S.W.P.P.P. I WILL LOOK TO SEE IF THERE IS ANY PARTICULAR NEEDS THAT NEED TO BE MET IN REGARDS TO LOT RELEASES OF THE HOMES. |