Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Inspection History Details
Inspection Status: Continued
Inspection History: GRADING - FINAL
Permit Number - T09BU01354
Inspection Description - GRADING - FINAL
Inspection Status - Continued
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
08/16/2013 | GRADING - FINAL | Continued | GOT WITH SHAWN WITH TMC ABOUT COMPLETING WORK ON AS-BUILTS. | |
08/16/2013 | GRADING - FINAL | Approved | ||
05/23/2013 | GRADING - FINAL | Continued | NO CHANGE TO PEDESTIAN BRIDGE FROM LAST INSPECTION. | |
05/20/2013 | GRADING - FINAL | Continued | NO CHANGE TO PEDESTIAN BRIDGE FROM LAST INSPECTION. | |
05/13/2013 | GRADING - FINAL | Continued | WALK SITE WITH SHAWN COLE PROJECT LEADER FOR TMC. TALKED ABOUT THE SAFTY HAZARD OF THE PEDESTRIAN BRIDGE. HE USED A HIGH PSI SPRAYER TO CLEAN THE BRIDGE BUT IT IS STILL SLIPPERY. HES WORKING ON BID FOR EPOXY PAINT. | |
05/08/2013 | GRADING - FINAL | Continued | WORKING ON LIST TO FINAL OUT PERMIT. | |
04/26/2013 | GRADING - FINAL | Continued | WALKED SITE WITH NEW GC .NEED CERT LETTER AND AS-BUILTS FOR FINAL INSPECTION. | |
03/26/2013 | GRADING - FINAL | Continued | COMPLET LIST FROM ELIZABETHS WALKING SITE. PROVIDE CERT LETTER FOR GRADING AND DRAINAGE. AND AS-BUILTS. | |
02/19/2013 | GRADING - FINAL | Not ready for Inspection | ||
08/09/2012 | GRADING - FINAL | Not ready for Inspection | COMPLET LIST FROM 6-26-2012. | |
06/26/2012 | GRADING - FINAL | Continued | WALKED SITE WITH SUPERINTENDENT. SITE WORK UNDER THIS PERMIT IS SUBSTANTIALLY COMPLETE. SUBMIT AN AS-BUILT PLAN TO THE CITY SHOWING ALL CHANGES MADE TO THE ORIGINAL GRADING PLAN. PROVIDE A CERTIFICATION STATEMENT FROM THE ENGINEER OF RECORD STATING THAT SITE WORK WAS SUBSTANTIALLY COMPLETED PER THE APPROVED PLANS. NO STORM WATER CONCERNS AT THIS TIME |
|
01/10/2012 | GRADING - FINAL | Continued | 1) INSPECTED INSTALL OF STORM DRAIN PIPING ALONG RING ROAD/CORRIGATED PLASTIC PIPE. TRENCH WAS COMPACTED, PIPE WAS BEDDED AND GRADED TO DRAIN PER APPROVED PLAN. AMOUNT OF PIPE INSTALLED WAS CHANGED/SEE REVISED PLAN. 2) INSPECTED PREPARATION OF CATCH BASIN INSTALL AT EAST END OF RING ROAD AT CROSSING. CHANGED FROM 1 SRP STORM DRAIN TO TWO SMALLER PIPES. 3) NO STORM WATER CONCERNS AT THIS TIME. 4) NEED CITY APPROVAL FOR BOTH CHANGES |
|
07/26/2011 | GRADING - FINAL | Continued | CONTRACTOR CALL IN INSPECTION IN ORDER TO KEEP THE PERMIT FROM EXPIRING. FINAL GRADING PERMIT WILL NOT BE APPROVED UNTIL ALL AREAS OF CONSTRUCTION HAVE BEEN STABILIZED. |
|
06/15/2011 | GRADING - FINAL | Continued | MAJORITY OF CONSTRUCTION HAS BEEN COMPLETED PER THE REVISED PLANS, HOWEVER SOME ISSUES REMAIN: 1) PARKING LOT ALONG SOUTH SIDE OF PEDIATRICS BLDG SHOWN ON PLANS NOT COMPLETED. 2) TWO UTILITY VAULTS ALONG NORTH SIDE NOT COMPLETED. 3) ALAMO BLDG DRAINAGE NOT COMPLETED. 4) STOCKPILE ALONG NORTH PROPERTY OFF MAIN SITE. POC FOR TMC BRIAN THOMZEDESKY 305-0363 |
|
02/24/2011 | GRADING - FINAL | Continued | ALL CONSTRUCTION WORK ON PROJECT WILL BE DONE IN VARIOUS PHASES, HOWEVER ALL WORK IS SHOWN ON THE APPROVED GRADING/SITE PLAN. ENSURE ALL CONDITIONS SHOWN UNDER THIS PERMIT ARE MET PRIOR TO FINAL APPROVAL. |
|
02/23/2011 | GRADING - FINAL | Continued | PRIOR TO FINAL APPROVAL CONTRACTOR MUST ENSURE PARKING AREA ACCROSS FROM NEW PEDIATRICS BLDG IS CONSTRUCTED PER APPROVED PLAN, IN ADDITION TO ALL THE OTHER REQUIREMENTS FOR FINAL APPROVAL | |
01/03/2011 | GRADING - FINAL | Continued | PRIOR TO FINAL APPROVAL FOR BORDERLAND CONSTRUCTION PHASE OF PROJECT, THE CONTRACTOR MUST: 1) PROVIDE AN APPROVED GRADING/SITE PLAN FOR FINAL GRADING INSPECTION. 2) PROVIDE A CERTIFICATION STATEMENT FROM THE ENGINEER OF RECORD STATING THAT STORM WATER DRAINAGE WAYS, CATCH BASINS, PIPING, AND RET/DET BASINS, WERE COMPLETED PER THE APPROVED PLAN. 3) COMPLETE ALL SITE WORK SHOWN ON PLANS. 4) COMPLETE ALL LANDSCAPING PER PLAN. |
|
10/05/2010 | GRADING - FINAL | Continued | 1) PRIOR TO FINAL APPROVAL BY ENGINNERING, CLEAN OUT SOIL FROM ALL EXISTING AND NEW CATCH BASINS. 2) PROVIDE A REVISED PLAN SHOWING CHANGES TO THE LOCATION/CONFIGURATION OF THE STORM DRAIN LINE AND TIE-IN TO RET/DET SYSTEM. 3) CONTRACTOR TO POUR CONCRETE COLLAR CONNECTION ON 24" STORM DRAIN LINE AT MH #1, #2 AND THE FLORR FOR MH#3. 4) 24" AND 15" CATCH BASINS (NYOPLAST) INSTALLED AT NE CORNER OF BLDG. 5) PICTURES TAKEN OF EACH CONNECTION, WE RE-INSPECT. 6) NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME. 7) ALL CHANGES TO STORM DRAINAGE CONFIGURATION, LOCATION, PIPE SIZES, MUST BE SHOWN ON AN APPROVED REVISED PLAN. |