Permit: T09BU01354

Parcel: 110120960


Addresses:

5301 E GRANT RD


Inspection Status: Continued

Inspection History: GRADING - FINAL

Permit Number - T09BU01354

Inspection Description - GRADING - FINAL

Inspection Status - Continued

Date Description Inspector Results Comments
08/16/2013 GRADING - FINAL Continued GOT WITH SHAWN WITH TMC ABOUT COMPLETING WORK ON AS-BUILTS.
08/16/2013 GRADING - FINAL Approved
05/23/2013 GRADING - FINAL Continued NO CHANGE TO PEDESTIAN BRIDGE FROM LAST INSPECTION.
05/20/2013 GRADING - FINAL Continued NO CHANGE TO PEDESTIAN BRIDGE FROM LAST INSPECTION.
05/13/2013 GRADING - FINAL Continued WALK SITE WITH SHAWN COLE PROJECT LEADER FOR TMC. TALKED ABOUT THE SAFTY HAZARD OF THE PEDESTRIAN BRIDGE. HE USED A HIGH PSI SPRAYER TO CLEAN THE BRIDGE BUT IT IS STILL SLIPPERY. HES WORKING ON BID FOR EPOXY PAINT.
05/08/2013 GRADING - FINAL Continued WORKING ON LIST TO FINAL OUT PERMIT.
04/26/2013 GRADING - FINAL Continued WALKED SITE WITH NEW GC .NEED CERT LETTER AND AS-BUILTS FOR FINAL INSPECTION.
03/26/2013 GRADING - FINAL Continued COMPLET LIST FROM ELIZABETHS WALKING SITE. PROVIDE CERT LETTER FOR GRADING AND DRAINAGE. AND AS-BUILTS.
02/19/2013 GRADING - FINAL Not ready for Inspection
08/09/2012 GRADING - FINAL Not ready for Inspection COMPLET LIST FROM 6-26-2012.
06/26/2012 GRADING - FINAL Continued WALKED SITE WITH SUPERINTENDENT. SITE WORK UNDER THIS PERMIT IS SUBSTANTIALLY COMPLETE.
SUBMIT AN AS-BUILT PLAN TO THE CITY SHOWING ALL CHANGES MADE TO THE ORIGINAL GRADING PLAN.
PROVIDE A CERTIFICATION STATEMENT FROM THE ENGINEER OF RECORD STATING THAT SITE WORK WAS SUBSTANTIALLY COMPLETED PER THE APPROVED PLANS.

NO STORM WATER CONCERNS AT THIS TIME
01/10/2012 GRADING - FINAL Continued 1) INSPECTED INSTALL OF STORM DRAIN PIPING ALONG RING ROAD/CORRIGATED PLASTIC PIPE. TRENCH WAS COMPACTED, PIPE WAS BEDDED AND GRADED TO DRAIN PER APPROVED PLAN. AMOUNT OF PIPE INSTALLED WAS CHANGED/SEE REVISED PLAN.
2) INSPECTED PREPARATION OF CATCH BASIN INSTALL AT EAST END OF RING ROAD AT CROSSING. CHANGED FROM 1 SRP STORM DRAIN TO TWO SMALLER PIPES.
3) NO STORM WATER CONCERNS AT THIS TIME.

4) NEED CITY APPROVAL FOR BOTH CHANGES
07/26/2011 GRADING - FINAL Continued CONTRACTOR CALL IN INSPECTION IN ORDER TO KEEP THE PERMIT FROM EXPIRING.
FINAL GRADING PERMIT WILL NOT BE APPROVED UNTIL ALL AREAS OF CONSTRUCTION HAVE BEEN STABILIZED.
06/15/2011 GRADING - FINAL Continued MAJORITY OF CONSTRUCTION HAS BEEN COMPLETED PER THE REVISED PLANS, HOWEVER SOME ISSUES REMAIN:

1) PARKING LOT ALONG SOUTH SIDE OF PEDIATRICS BLDG SHOWN ON PLANS NOT COMPLETED.
2) TWO UTILITY VAULTS ALONG NORTH SIDE NOT COMPLETED.
3) ALAMO BLDG DRAINAGE NOT COMPLETED.
4) STOCKPILE ALONG NORTH PROPERTY OFF MAIN SITE.

POC FOR TMC BRIAN THOMZEDESKY 305-0363
02/24/2011 GRADING - FINAL Continued ALL CONSTRUCTION WORK ON PROJECT WILL BE DONE IN VARIOUS PHASES, HOWEVER ALL WORK IS SHOWN ON THE APPROVED GRADING/SITE PLAN.
ENSURE ALL CONDITIONS SHOWN UNDER THIS PERMIT ARE MET PRIOR TO FINAL APPROVAL.
02/23/2011 GRADING - FINAL Continued PRIOR TO FINAL APPROVAL CONTRACTOR MUST ENSURE PARKING AREA ACCROSS FROM NEW PEDIATRICS BLDG IS CONSTRUCTED PER APPROVED PLAN, IN ADDITION TO ALL THE OTHER REQUIREMENTS FOR FINAL APPROVAL
01/03/2011 GRADING - FINAL Continued PRIOR TO FINAL APPROVAL FOR BORDERLAND CONSTRUCTION PHASE OF PROJECT, THE CONTRACTOR MUST:

1) PROVIDE AN APPROVED GRADING/SITE PLAN FOR FINAL GRADING INSPECTION.
2) PROVIDE A CERTIFICATION STATEMENT FROM THE ENGINEER OF RECORD STATING THAT STORM WATER DRAINAGE WAYS, CATCH BASINS, PIPING, AND RET/DET BASINS, WERE COMPLETED PER THE APPROVED PLAN.
3) COMPLETE ALL SITE WORK SHOWN ON PLANS.
4) COMPLETE ALL LANDSCAPING PER PLAN.
10/05/2010 GRADING - FINAL Continued 1) PRIOR TO FINAL APPROVAL BY ENGINNERING, CLEAN OUT SOIL FROM ALL EXISTING AND NEW CATCH BASINS.
2) PROVIDE A REVISED PLAN SHOWING CHANGES TO THE LOCATION/CONFIGURATION OF THE STORM DRAIN LINE AND TIE-IN TO RET/DET SYSTEM.
3) CONTRACTOR TO POUR CONCRETE COLLAR CONNECTION ON 24" STORM DRAIN LINE AT MH #1, #2 AND THE FLORR FOR MH#3.
4) 24" AND 15" CATCH BASINS (NYOPLAST) INSTALLED AT NE CORNER OF BLDG.
5) PICTURES TAKEN OF EACH CONNECTION, WE RE-INSPECT.

6) NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME.

7) ALL CHANGES TO STORM DRAINAGE CONFIGURATION, LOCATION, PIPE SIZES, MUST BE SHOWN ON AN APPROVED REVISED PLAN.