Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit: T09BU01354

Parcel: 110120960


Addresses:

5301 E GRANT RD


Inspection Status: Approved

Inspection History: GRADING - TIER REV

Permit Number - T09BU01354

Inspection Description - GRADING - TIER REV

Inspection Status - Approved

Date Description Inspector Results Comments
08/16/2013 GRADING - TIER REV Approved
08/16/2013 GRADING - TIER REV Approved
08/09/2012 GRADING - TIER REV Continued
03/06/2012 GRADING - TIER REV Continued 1) CHANGES MADE TO THE RING ROAD CULVERT CROSSING, SLOT DRAIN, AND CATCH BASIN LOCATED ALONG THE NE CORNER OF THE SITE ACCROSS FROM THE EXISTING PARKING GARAGE. WILL VARIFY CHNAGES AS CONSTRUCTION BEGINS NXT WEEK.
2) TOOK PICTURES OF HEADWALL CONSTRUCTION AT CHANNEL CROSSING OF RING ROAD ALONG THE NW CORNER OF THE SITE. PROPOSED CATCH BASIN CHANGE AT THIS LOCATION ALSO.
3) PREPARATION FOR PAVING AND POURING CURBS AT NEW PARKING STUCTURE. WILL VERIFY SITE WORK COMPARED TO APPROVED PLANS.
01/10/2012 GRADING - TIER REV Continued 1) INSPECTED INSTALL OF STORM DRAIN PIPING ALONG RING ROAD/CORRIGATED PLASTIC PIPE. TRENCH WAS COMPACTED, PIPE WAS BEDDED AND GRADED TO DRAIN PER APPROVED PLAN. AMOUNT OF PIPE INSTALLED WAS CHANGED/SEE REVISED PLAN.
2) INSPECTED PREPARATION OF CATCH BASIN INSTALL AT EAST END OF RING ROAD AT CROSSING. CHANGED FROM 1 SRP STORM DRAIN TO TWO SMALLER PIPES.
3) NO STORM WATER CONCERNS AT THIS TIME.

4) NEED CITY APPROVAL FOR BOTH CHANGES
12/23/2011 GRADING - TIER REV Continued CHANGES MADE TO STORM DRAIN PIPING AT STREET CROSSING ALONG NE CORNER OF SITE.
HAVE DRAWING FROM THE ENGINEER OF RECORD SHOWING THE CHANGES MADE AND HOW THE DIFFER FROM THE CITY APPROVED PLAN.
WILL ASK REVIEWER IF CONTRACTOR NEEDES TO SUBMIT A REVISION TO THE CITY.

NO STORM WATER CONCERNS AT THIS TIME
02/10/2011 GRADING - TIER REV Continued Revision: jet fuel tank near helipad relocated from underground to above ground and added screen wall.
08/20/2010 GRADING - TIER REV Continued CHANGES TO STORM DRAINAGE SYSTEM PIPING LOCATION AND SIZING ALONG THE SOUTH SIDE OF THE MAIN HOSP BLDG. A REVISED PLAN SHOWING ALL SITE CHANGES MADE HAS BEEN SUBMITTED TO COT AND APPROVED.

PLEASE CALL FOR INSPECTION FOR ALL SUBGRADE PIPING PRIOR TO COVER, TO INCLUDE MANHOLES AND CATCH BASINS.

WILL REVIEW AND INSPECT OFF OF NEW REVISED GRADING PLAN.

NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME
08/20/2010 GRADING - TIER REV Continued 1) PRIOR TO FINAL APPROVAL BY ENGINNERING, CLEAN OUT SOIL FROM ALL EXISTING AND NEW CATCH BASINS.
2) PROVIDE A REVISED PLAN SHOWING CHANGES TO THE LOCATION/CONFIGURATION OF THE STORM DRAIN LINE AND TIE-IN TO RET/DET SYSTEM.
3) CONTRACTOR TO POUR CONCRETE COLLAR CONNECTION ON 24" STORM DRAIN LINE AT MH #1, #2 AND THE FLORR FOR MH#3.
4) 24" AND 15" CATCH BASINS (NYOPLAST) INSTALLED AT NE CORNER OF BLDG.
5) PICTURES TAKEN OF EACH CONNECTION, WE RE-INSPECT.

6) NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME.