Inspection History Details
Inspection Status: Approved
Inspection History: ENGINEERING PRE-CONSTRUCTION
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/04/2010 | ENGINEERING PRE-CONSTRUCTION | Approved | ||
| 02/25/2010 | ENGINEERING PRE-CONSTRUCTION | Partial Approval | SITE IS ACTUALLY SPLIT INTO TWO SMALLER PROJECTS: ONE PROJECT IS THE CONSTRUCTION OF A NEW PEDIACTRIC BLDG AND ADJACENT UNDERGROUND RET/DET BASIN, BEING MANAGED BY LLOYD CONSTR. AND THE SECOND PROJECT IS THE RE-WORK OF THE PARKING AREA AND SUROUNDING PEDESTRIAN PATHWAY BEING CONSTRUCTED BY BODERLAND (TREVEN 490-3099). THE BLDG PROJECT HAS STARTED AND HAS ADDRESSED STORM WATER CONCERNS BY USING SILT SOCK ALONG THE WEST SIDE AND THE EXISTING CURBING AROUND THE REST. CONTRACTOR WILL PROTECT EXISTING STORM DRAIN SYSTEM AND SWEEP UP TRACKING ON A ROUTINE BASIS. THE BODERLAND PROJECT HAS NOT STARTED. CHANGED FROM AP TO PA FOR REINSPECTION |