Inspection Status: Approved
Inspection History: GRADING - INTERMEDIATE
| Date |
Description |
Inspector |
Results |
Comments |
| 01/25/2011 |
GRADING - INTERMEDIATE |
|
Approved |
Approved |
| 01/14/2011 |
GRADING - INTERMEDIATE |
|
Continued |
Site all paved, contractor spoke to planning downtown about eliminating a planter next to the HC parking but was told that the planter is required. Most LS in place, will call for final next week |
| 12/29/2010 |
GRADING - INTERMEDIATE |
|
Continued |
Paving complete, checked slope on HC parking and is OK. |
| 12/17/2010 |
GRADING - INTERMEDIATE |
|
Continued |
Talked to contractor about moving HC parking stall one space to the east to better match the existing grade, I told him that was OK, also discussed the outlet for the downspout scupper under the sidewalk on north side of building, the asphalt will need to be replaced to allow for flow from the scupper. |
| 12/09/2010 |
GRADING - INTERMEDIATE |
|
Continued |
Contractor has dumpster pad and valley gutter formed and ready to pour, OK to pour dumpster pad and gutter. |
| 11/29/2010 |
GRADING - INTERMEDIATE |
|
Continued |
Site work around building underway. |
| 10/05/2010 |
GRADING - INTERMEDIATE |
|
Continued |
Contractor continuing to work on building, will start to finish grade around building in about 3 weeks. |
| 07/14/2010 |
GRADING - INTERMEDIATE |
|
Continued |
Work continues on new building |
| 06/17/2010 |
GRADING - INTERMEDIATE |
|
Partial Approval |
OK to use new parking lot in front of existinf Bldg. |
| 05/18/2010 |
GRADING - INTERMEDIATE |
|
Continued |
Met with contractor to discuss temporary parking while construction is under way, told him he needs an all weather surface and 24ft paal. |
| 05/06/2010 |
GRADING - INTERMEDIATE |
|
Continued |
Rough grading complete, no activity on building. |
| 04/22/2010 |
GRADING - INTERMEDIATE |
|
Continued |
grading of site began, will monitor track out. |
| 03/04/2010 |
GRADING - INTERMEDIATE |
|
Continued |
No activity |