Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Permit: T09BU00917

Parcel: 10705126B


Addresses:

801 W MIRACLE MILE

Inspection Status: Approved

Inspection History: STORMWATER FOLLOW-UP INSP

Date Description Inspector Results Comments
08/19/2010 STORMWATER FOLLOW-UP INSP Approved
06/29/2010 STORMWATER FOLLOW-UP INSP Continued 1) CHANGES TO SIDEWALKS/ AND SIDEWALK LOCATIONS. REVISE PLANS TO SHOW NEW LOCATIONS.

2) COURTYARD WALKWAYS WERE NOT INSTALLED PER COT STD 200 AS SHOWN ON APPROVED PLANS. REVISE PLANS TO SHOW CHANGES AND WALKWAYS MUST BE A MIN OF 4'.

3) ENSURE RUN SLOPES ON ALL ACCESS WAY AND SIDEWALKS DO NOT EXCEED 5%.

4) SWEEP UP TRACKING OFF PUBLIC ROADWAYS ALONG WEST SIDE.

5) PRIOR TO APPROVAL BY ENGINEERING FOR A C OF O, COMPLETE ALL SITE WORK ASSOCIATED WITH THE BLDG AND PHYSICALLY SEPARATE REMAINING CONSTRUCTION WITH THE PUBLIC.
06/10/2010 STORMWATER FOLLOW-UP INSP Continued WALKED SITE W/SUPINTENDENT, NO ADDITIONAL CHANGES FROM REVISED GRADING PLAN. PHASE TWO OF PROJECT IS AT CITY FOR REVIEW, SITES WILL WORK TOGETHER AS FAR AS DRAINAGE AND ACCESS.
SOME CONCERN ABOUT ROOF FROM BLDG SHEET FLOW ONTO PLANTER (12" WIDE) NEXT TO SIDEWALK, W/ NO SCUPPERS IN SIDEWALK LOCATED AT THE SOUTH END OF SITE.

CONTRACTOR PRESERVED TWO EUCALYPTUS TREES ALONG EAST SIDE, OWNER PLANTING ADDITIONAL PLANTS COMPARED TO LANDSCAPE PLAN.

NO STORM WATER CONCERNS AT THIS TIME
03/30/2010 STORMWATER FOLLOW-UP INSP Continued MULTIPLE BLDGS BEING REFURBISHED ON SITE, SOME DIRT WORK BEING ACCOMPLISHED. NO SITE WORK BEING DONE CURRENTLY. NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME. CONTRACTORS ON SITE MUST ENSURE THAT THEY DISPOSE OF ANY CONSTRUCTION WASTE PROPERLY
01/27/2010 STORMWATER FOLLOW-UP INSP Continued FOOTER BEING DUG FOR SCREEN WALL ALONG SOUTH SIDE, SPOILS ARE BEING PLACED ON INSIDE EDGE OF TRENCH.
PERIMETER OF SITE MUST BE SWEPT ROUTINELY UNTIL SITE IS HARDSCAPED, PAVED AND/OR STABILIZED
01/20/2010 STORMWATER FOLLOW-UP INSP Correction Required "V" DITCH ALONG SOUTH SIDE USED FOR SEDIMENT CONTROL HAS BEEN REMOVED, CONTRACTOR CURRENTLY HAS NO SWPPP CONTROLS IN PLACE
ALTHOUGH THE SITE DOES NOT HAVE A STORM WATER POLLUTION PREVENTION PLAN, CONTRACTOR MUST ENSURE THAT DISTURBED SOIL STAYS ON SITE.

LOTS OF DEMO ON SITE
CONTRACTOR CONTINUES TO BURN WASTE ON SITE
GRADING LIMIT FOR CURRENT ACTIVE GRADING PERMIT NOT CLEARLY MARKED.
01/08/2010 STORMWATER FOLLOW-UP INSP Continued A COMPACTED "V" DITCH HAS BEEN CONSTRUCTED ALONG THE SOUTH PERIMETER TO ACT AS TEMP SEDIMENT CONTROL UNTIL THE PERIMETER WALL IS CONSTRUCTED. CONTRACTOR MUST CONTINUE TO SWEEP UP TRACKED SOIL OFF OF PUBLIC ROADWAYS AS NEEDED. CONTRACTOR MUST ADD SUPPLEMENTAL SEDIMENT CONTROLS IF NEEDED THROUGHOUT CONSTRUCTION.